powering on

$360M DOE grant to fund project that will connect ERCOT to US power grid

For the first time, Texas's ERCOT grid will be connected to other states' grids thanks to funding from the Department of Energy. Photo via Getty Images

Thanks to recently announced funding, the power grid for the territory served by the Electric Reliability Council of Texas (ERCOT) will be connected to grids in other states.

Officials hope building a 320-mile transmission line that connects the ERCOT electric grid to electric grids in the Southeast will prevent power outages like the massive blackout that occurred in 2022 when a winter storm blasted Texas.

San Francisco-based Pattern Energy says its Southern Spirit project will cost more than $2.6 billion. Full-scale construction is supposed to get underway in 2028, and the project is set to go online in 2031.

The U.S. Department of Energy recently approved up to $360 million for the transmission project. The transmission line will stretch from Texas’ border with Louisiana to Mississippi. It’ll supply about 3,000 megawatts of electricity in either direction. That’s enough power for about 750,000 residential customers during ERCOT’s peak hours.

ERCOT’s more than 54,100 miles of transmission lines supply power to about 90 percent of Texans.

“The U.S. transmission network is the backbone of our nation’s electricity system. Though our grid has served U.S. energy needs for more than a century, our country’s needs are changing,” David Turk, under secretary at the Department of Energy, says in a news release.

“DOE’s approach to deploying near-term solutions and developing long-term planning tools will ensure our electric grid is more interconnected and resilient than ever before,” Turk adds, “while also supporting greater electricity demand.”

The other three projects that recently received funding from the DOE include:

  • Aroostook Renewable Project, which will construct a new substation in Haynesville, Maine, and a 111-mile transmission line connecting to a substation in Pittsfield, Maine.
  • Cimarron Link, a 400-mile HVDC transmission line from Texas County, Oklahoma to Tulsa, Oklahoma
  • Southline, which will construct a 108-mile transmission line between Hidalgo County, New Mexico, and Las Cruces, New Mexico. The DOE previously supported a 175-mile line from Hidalgo County, New Mexico, to Pima County, Arizona, in Southline Phase 1 on the first round of the Transmission Facilitation Program.

This month's funding completes the $2.5 billion in awards from the Transmission Facilitation Program which is administered through the Building a Better Grid Initiative that launched in January 2022. Its mission has been to develop nationally significant transmission lines, increase resilience by connecting regions of the country and improve access to clean energy sources, according to the DOE.

Earlier this year, ERCOT, which manages 90 percent of Texas’ power supply, forecasted a major spike in demand for electricity over the next five to seven years

Trending News

A View From HETI

Fervo's Cape Station geothermal project is ahead of schedule. Photo courtesy Fervo Energy

Fervo Energy’s flagship project in Utah just generated its first geothermal power.

The electricity is now flowing to the power grid from one of Cape Station’s three generation units, Houston-based Fervo said in a news release. This represents an early but important milestone for the project, as the unit isn’t scheduled to deliver contracted power until Oct. 1.

The achievement, coming four months after Fervo’s roughly $2.2 billion IPO, demonstrates the viability of enhanced geothermal systems (EGS).

“This is a gamechanger for the geothermal industry. It establishes EGS as the defining new power generation technology of our time, and we believe it shows that the commercial and technical maturity of EGS is ready to meet the urgent need for reliable, clean power,” Tim Latimer, co-founder and CEO of Fervo, said in the release.

The plant’s two other units are scheduled to launch commercial operations on Jan. 1.

The three units make up the project’s 99-megawatt first phase. The next phase, which will add 400 megawatts of capacity, is under construction. The second phase is set to go online in 2028.

Altogether, Cape Station will provide more than 4 gigawatts of capacity, with 900 megawatts already spoken for. The 900 megawatts of contracted electricity would be enough to power nearly 1 million U.S. homes per year.

“Cape Station works because we treated the subsurface like an engineering challenge,” Jack Norbeck, co-founder and chief technology officer of Fervo, added in the release. “Years of drilling, completion design, subsurface modeling, and flow testing led to this moment, and this is the validation that matters most.”

Enhanced geothermal continuously draws on heat that’s deep underground, producing electricity around the clock regardless of weather or time of day. That makes it one of the only carbon-free resources capable of constant power delivery, which is critical for data centers and AI infrastructure.

Trending News