power deal

Chevron eyes $7B Texas power plant for Microsoft data center campus

Chevron is in talks with Microsoft and Engine No. 1 about a massive natural gas power plant in Texas. Photo via Getty Images

Software giant Microsoft is negotiating exclusively with Houston-based oil and gas titan Chevron and investment firm Engine No. 1 about the development of a $7 billion power plant in West Texas that would supply electricity for a Microsoft data center campus.

The proposed natural-gas-fired plant initially would generate 2,500 megawatts of electricity, Bloomberg reports. The plant would be built near Pecos, a Permian Basin city, in an area where Microsoft plans to build a 2,500-megawatt data center campus on a 7,000-acre site.

A deal with Microsoft would secure a long-term customer for the plant’s output and help finance its construction, Bloomberg says. The project, expected to be producing power by 2030, still requires tax and environmental approvals as well an agreement to terms among Chevron, Engine No. 1, and Microsoft.

In a statement issued after Bloomberg reported the news, Chevron acknowledged it was in exclusive talks with Engine No. 1 and Microsoft, but the oil and gas company offered no details.

Chevron says the proposed plant “reflects an emerging shift in how power for AI is being developed, bringing energy supply closer to demand through co-located, behind-the-meter generation to deliver reliability while helping avoid added strain on regional electricity systems. It pairs sustained, always-on demand from advanced computing with proven capability to design, build, and operate large-scale energy infrastructure.”

Development of gas-powered electrical plants for AI data centers represents a new—and potentially lucrative— business line for Chevron. In 2025, Chevron, Engine No. 1 and GE Vernova announced a partnership to produce natural gas for AI data centers in the U.S.

Chevron’s collaboration with Engine No. 1 has already secured an order for seven large natural gas turbines from GE Vernova, according to Bloomberg.

“Energy is the key to America’s AI dominance,” Chris James, founder and chief investment officer of Engine No. 1, said last year. “By using abundant domestic natural gas to generate electricity directly connected to data centers, we can secure AI leadership, drive productivity gains across our economy, and restore America’s standing as an industrial superpower.”

Trending News

A View From HETI

Hurricane season began June 1. Photo via Pexels

As hurricane season descends upon the region, CenterPoint Energy has shared the latest update on its Greater Houston Resiliency Initiative (GHRI) that’s been working to make grid upgrades and introduce weather-related tech since 2024.

As of April 2026, CenterPoint had:

  • Replaced more than 65,000 poles with stronger storm-resistant infrastructure
  • Trimmed or cleared more than 10,000 miles of vegetation
  • Undergrounded more than 500 miles of power lines
  • Installed more than 600 automation devices
  • Installed more than 150 weather stations

In May, CenterPoint announced its new Community Progress Tracker, which helps residents track electronic infrastructure improvements. In terms of other technology, CenterPoint has announced its partnership with weather, wildfire and flood modeling software Technosylva. The software is expected to help CenterPoint track weather conditions in advance to better prepare crews.

CenterPoint has also added 150 weather stations to improve weather monitoring, conducted a full-scale hurricane response exercise involving more than 400 employees and completed more than 25,000 hours of FEMA training across more than 800 employees. The company opened a new year-round Emergency Operations Center to help coordinate with emergency response partners, local and state officials, and media during major weather events.

“We are proud of the progress made in 2025, which helped deliver more than 100 million fewer outage minutes when compared to 2024, and we are determined to make even more progress in 2026 as we work toward our defining goal: building the nation's most resilient coastal grid,” Nathan Brownell, CenterPoint's vice president of resilience and capital delivery, previously said in a news release.

According to the company, the GHRI aims to improve overall grid resiliency and reliability and to reduce outages for customers. CenterPoint projects its efforts can reduce customer outages by 150 million by the end of 2026.