Scotty Nyquist discuss the growth in AI data centers and the strain on the system. Photo via HARC report

For most of the past 20 years, U.S. electricity policy relied on predictable trends in demand. Electricity use, in most regions, increased gradually, forecasts were stable, and utilities adjusted the system in small steps. Power plants, transmission lines, and substations were generally added to reflect shifts in load, rather than growth, and costs were recovered through modest adjustments to customer bills.

Growth in AI data centers has disrupted this model. A single facility can add as much electricity demand as a small town. That demand comes all at once, runs continuously, and has little tolerance for outages. If electricity service drops even briefly, computation stops, and services shut down. Ironically, data centers need reliable service, a point that their emergence is driving concern around for the rest of the grid.

What the numbers say

The International Energy Agency projects global electricity consumption from data centers to double by 2030, reaching roughly 945 TWh, nearly 3 percent of global electricity demand, with consumption growing about 15 percent per year this decade. McKinsey projects that U.S. data center demand alone could grow 20–25 percent per year, with global capacity demand more than tripling by 2030.

After years of roughly 0.5 percent annual demand growth, many forecasts now place total U.S. electricity demand growth closer to 2–3 percent per year through the mid-2030s, with much higher growth in specific regions. In Texas, some forecasters are saying electricity demand could double over the next five years, a staggering 10 percent per year growth rate. What sounds incremental on paper translates into a major challenge on the ground. Meeting this pace of growth is estimated to require $250–$300 billion per year in grid investment, about double what the system has been absorbing.

Where the system starts to strain

The strain appears first in the interconnection queue. It shows up as long waits, backlogs, and delays for connecting new loads and new generation.

Before new generators or large load customers can be connected, a study is required to assess their impact on the grid, whether it can physically handle the added load, and whether upgrades are required. With AI-driven data centers, utilities face far more connection requests than they can realistically support. In ERCOT, large-load interconnection requests exceed 200 gigawatts, most tied to data centers. That amount exceeds historical norms, and it is several times larger than what can be practically studied or built in the near term.

To be clear, public utility commissions are required to study these requests because they must manage system capabilities to ensure minimal disruption. This means engineers spend time evaluating projects that may never be built, while other more commercially viable projects may wait longer for approvals. This extends timelines and makes infrastructure planning less reliable.

Why policymakers are rethinking the rules

Utilities and their regulators must decide how much generation, transmission, and substation capacity to build years before it comes online. Those decisions are based on expected demand at the time projects are approved. When it comes to data centers, by the time infrastructure is completed, they may end up deploying newer, more efficient chips that use less power than originally assumed. This can result in grid infrastructure built for a higher load than what actually materializes, leaving excess capacity that still must be paid for through system-wide rates.

That’s the central dilemma. If utilities build too little capacity, the system operates with less reserve margin. During periods of grid stress, operators have fewer options, increasing the likelihood of curtailments or outages. However, if utilities build too much, customers may be asked to pay for infrastructure that is not fully used.

In response, policymakers are adjusting the rules. In some regions, regulators are moving toward bring-your-own-power approaches that require large data centers to supply or fund part of the capacity needed to serve them or reduce demand during system stress. At the federal level, permitting reforms tied to datacenter infrastructure increasingly treat electricity as a strategic economic input.

As Ken Medlock, senior director at the Baker Institute Center for Energy Studies (CES), explains:

“Many of the planned data centers are now also adding behind-the-meter options to their development plans because they do not anticipate being able to manage their needs solely from the grid, and they certainly cannot do so with only intermittent power sources.”

Behind-the-meter (BTM) refers to power that a consumer controls on its side of the utility meter, such as on-site gas generation or a dedicated power plant. These resources allow data centers to keep operating during grid-related service. Most facilities remain connected to the grid, but the backup BTM generation serves as insurance for operating their core business.

This shifts responsibility. Utilities traditionally manage reliability across all customers by maintaining an operating reserve margin, or spare capacity. Increasingly, large-load customers manage part of their own electricity reliability needs, which changes how infrastructure is planned and how risk is distributed.

Bottom line

AI-driven load growth is arriving faster and in more concentrated places than the power system was built to accommodate. Utilities and regulators are being forced to make decisions sooner than planned about where to build, how fast to build, and which customers get priority when capacity is limited. The effects extend beyond data centers, showing up in system costs, reliability margins, competition for grid access, and pressure on communities and industries that depend on affordable and dependable power. The issue is not whether electricity can be generated, but how the costs and risks of rapid demand growth are distributed as the system tries to keep up. How regulators balance these decisions will determine who pays as AI demand outruns the power grid.

-----------

Scott Nyquist is a senior advisor at McKinsey & Company and vice chairman, Houston Energy Transition Initiative of the Greater Houston Partnership. The views expressed herein are Nyquist's own and not those of McKinsey & Company or of the Greater Houston Partnership. This article originally appeared on LinkedIn.

VoltaGrid has developed a modular power generation system that improves reliability and limits emissions. Photo via voltagrid.com

Houston startup lands $1B from Blackstone and Halliburton, plans acquisition

power deal

Houston-based power generation startup VoltaGrid has nailed down a $1 billion equity investment from asset management heavyweight Blackstone and Houston-based oilfield services provider Halliburton.

The investment comes in two forms:

  • A $775 million primary capital raise
  • A $225 million secondary capital purchase from existing investors

VoltaGrid, founded in 2020, provides behind-the-meter mobile power generation equipment for data centers, microgrids and industrial customers.

Aside from the $1 billion investment, VoltaGrid has agreed to buy Propell Energy Technology, a VoltaGrid supplier, for an undisclosed amount. Propell offers a natural gas power generation platform for AI data centers. VoltaGrid plans to add two manufacturing plants at Propell’s facilities in Granbury, a Dallas-Fort Worth suburb.

The investment and acquisition deals are expected to close in mid-2026.

Funds managed by Blackstone Tactical Opportunities are contributing to the $1 billion investment. William Nicholson, managing director of Blackstone, called VoltaGrid “a highly differentiated platform addressing one of the most important infrastructure needs of the AI era: reliable, rapidly deployable power. This investment is a strong example of Tac Opps’ focus on providing flexible, scaled capital to exceptional entrepreneurs and businesses operating in Blackstone’s highest-conviction investment themes.”

Nathan Ough, founder and CEO of VoltaGrid, said in a release that the Blackstone investment “is a powerful endorsement of the platform we have built and the role VoltaGrid is playing in delivering the energy infrastructure of the AI era.”

Last October, VoltaGrid and Halliburton said they had forged a partnership to supply power for data centers around the world, with the Middle East picked as the initial target. Two months later, the companies said they had arranged the manufacturing of 400 megawatts of natural gas power systems that’ll be delivered in 2028 to support new data centers in the Eastern Hemisphere.

Jeff Miller, president and CEO of Halliburton, said his company’s investment in VoltaGrid “reflects our shared focus on long-term solutions for the world’s most demanding power environments, and advances VoltaGrid’s ability to deliver reliable, distributed power at scale.”

Fort Bliss. Photo via army.mil

Texas data center proposed by U.S. Army could use more power than El Paso

Big Data

The U.S. Army is proposing developing a gargantuan, 3-gigawatt data center complex on Fort Bliss property that within a few years would consume more electricity than all of El Paso Electric’s 460,000 customers combined – even as questions about its development, water usage and air pollution remain unanswered.

If built, it would be the third major data center project in the El Paso region, along with Meta Platform’s $10 billion facility in Northeast and the $165 billion Project Jupiter campus that Oracle and OpenAI are building in Santa Teresa, New Mexico. The combined scale and size of the three facilities could quickly transform the Borderland into one of the nation’s core hubs of power generation and AI infrastructure.

The publicly-traded investment firm Carlyle Group would pay to build and operate the Fort Bliss data center – one of several planned in a national rollout under President Donald Trump’s administration to rapidly increase artificial intelligence technology for the Department of Defense.

At Fort Bliss, the Army is “targeting an initial operating capacity of about 100 megawatts on the compute side” by next year, David Fitzgerald, deputy undersecretary of the Army, said during a meeting with reporters April 22. An official estimated cost for the project has yet to be released.

By 2029, the complex on military land in far East El Paso would require 3 gigawatts of electricity, Fitzgerald said. By comparison, El Paso Electric currently maintains about 2.9 gigawatts of generation capacity across its entire system that spans from Hatch, New Mexico, to Van Horn, Texas. The highest customer demand the power company has ever seen was just over 2.3 gigawatts during the summer of 2023.

And whether most El Pasoans are on board with the rapid buildout of another data center here is not a question that Army leadership is asking at this point.

“What we’re trying to do is find where are the common interests, common ground that we can solve for?” Fitzgerald said, referring to coordinating with El Paso city leaders on the data center project.

“The state of modern warfare and future warfare is largely going to depend on the ability to capture, process and utilize massive amounts of data,” he said. “So, the reality is, this is a strategic priority, not just for the Army, but for the entire Department of War. So, we need these capabilities, and we need to put them somewhere.”

Combined-cycle natural gas turbines are the “most likely” source of electricity generation for the facility, said Jeff Waksman, an assistant secretary of the Army and former member of Trump’s first administration.

Waksman said the facility would undergo environmental review before construction starts.

Still, there are far more outstanding questions than answers about the proposed Fort Bliss data center.

It’s unclear if the facility would connect to El Paso Water’s water system. The city-owned water utility pointed out that Fort Bliss Water provides water service for the installation. However, El Paso Water can provide “backup” service to the base, according to the project solicitation documents.

“EPWater was just recently brought into the discussion, and we only have preliminary information,” El Paso Water said in a statement. “The construction and water use would be entirely on federal property.”

El Paso Electric said it’s also uncertain whether the data center will connect to the utility’s power grid and will figure that out in the future. To date, the Army hasn’t made a formal request for service from El Paso Electric.

Officials from the U.S. Army “confirmed that questions regarding the power source and whether it will be connected to the regional grid remain under review and have plans to establish a data center with a projected demand of 3 gigawatts,” El Paso Electric said in a statement. “Ultimately, decisions about these matters will be made by Fort Bliss leadership, and we defer to them for further comment.”

A representative with Carlyle Group at a recent community meeting didn’t answer questions or provide details about the proposed data center facility and the related power generation source.

Carlyle Group did not respond to a request for comment.

Army officials said they don’t yet have a definitive agreement in place with Carlyle, which was conditionally selected to enter into exclusive negotiations, so few details are finalized.

However, the Army has set a short timeline to start operating by late 2027. That means construction will have to start soon, Fitzgerald said.

“The ideal endstate is that we would be at least (operational) by the end of ’27, which is moving pretty quick,” Fitzgerald said. “That would mean construction would need to begin in the not-so-distant future.”

Water, electricity concerns

Meeting three gigawatts of electricity demand with natural gas-fired turbines – cited by Army officials as the most likely power source – would likely produce huge amounts of greenhouse gases in a central area of El Paso, such as carbon dioxide, as well as other harmful pollutants including particulate matter.

And even if the data center doesn’t take service from El Paso Water and instead receives water from wells managed by Fort Bliss, it would rely on groundwater pumped out of the Hueco Bolson aquifer, the city’s main source of water.

The solicitation issued by the Army cites water risk for El Paso as “extremely high” and notes that most of Fort Bliss’ water supply comes from wells within the installation.

Fitzgerald said the Army is aware of the public’s concern that the data center could unsustainably guzzle El Paso’s groundwater to cool the data center’s computer servers. He said the facility will be “water neutral.”

It’s also not clear how the project could replace the same amount of water that it consumes.

It’s possible the Kay Bailey Hutchison Desalination Plant – co-owned by El Paso Water and the U.S. Army – could play a role in making the data center water neutral. But El Paso Water said it has no details about how the data center facility could achieve water neutrality.

El Paso Water is “more than willing to continue to share ideas for best practices in sustainability to help protect our regional water resources,” the utility said in its statement.

As far as electricity generation, Army officials said they don’t know if El Paso Electric would build a new power plant to serve the data center. It’s also possible that Carlyle Group or another private company could build its own power generation source for the data center that’s isolated from the power grid El Pasoans use every day.

“We have to decide whether El Paso Electric is going to be the ones building whatever is coming, or if this is going to be some independent power producer,” Waksman said.

El Paso Electric is planning to develop a 366 megawatt power plant made up of over 800 small gas generators to power Meta’s data center. The utility will build more generation in the coming years to meet 1 gigawatt of total demand from Meta’s facility. Meanwhile, as the technology giant Oracle develops Project Jupiter, the company said Monday it is seeking to power the campus using 2.45 gigawatts of fuel cell power systems provided by the company Bloom Energy.

For perspective, 3.45 gigawatts – the combined projected demand of those two major data centers – is enough electricity to power as many as a million homes, depending on the time of day and weather.

The Fort Bliss project would have to meet environmental regulatory requirements, and the developer needs to include a plan for providing utilities and infrastructure needs such as access to the facility, according to a request for proposals issued by the Army in December 2025. Army officials emphasized the project would not impact El Pasoans’ water or electric bills.

Who is Carlyle Group?

Carlyle Group is a global investment management firm that oversees $477 billion of assets from entities such as pension funds.

The company invests that money by buying businesses ranging from wine producers to Asian telecommunications companies, or by developing infrastructure projects such as renewable energy generation and data centers. The company in 2025 posted distributable earnings of nearly $1.7 billion on $4.8 billion in revenue.

The Army wants to build the facility at Fort Bliss in partnership with Carlyle because the installation has a large amount of available, unused land and because of the water and electricity infrastructure already in place in El Paso, Fitzgerald said.

The Carlyle data center planned for El Paso is part of a wider U.S. military effort to quickly build infrastructure that supports the use of artificial intelligence — both on the battlefield and in running its day-to-day operations, according to government documents.

Army officials nodded to the use of AI in drone warfare and targeting systems. And a hyperscale data center facility can also securely house information such as the military’s cloud database that details pay and entitlements for every U.S. soldier, said Maj. Gen. Curtis Taylor, commanding general of the 1st Armored Division and Fort Bliss.

Data centers are “essential parts of power projection,” Taylor said. “But we have to protect those servers. And that’s why there’s great utility in building that infrastructure on military installations.”

The Fort Bliss facility would be located on a plot of land near the intersection of Loop 375 and Montana Avenue. The site is just east of the Camp East Montana immigrant detention facility, and near El Paso Electric’s gas-fired Montana power station.

The plan is for Carlyle to utilize the majority of the data center’s capacity for its business needs, and the military would have access to a more secure portion of the data center for its own uses.

The Army is developing another similar data center project in Dugway, Utah. Other Army bases identified as potential sites include Fort Hood in Texas and Fort Bragg in North Carolina.

The U.S. Air Force in October issued a solicitation saying it is “accepting proposals for the development of Artificial Intelligence data centers,” on unused land at different bases, including in California, Georgia, Arizona and Tennessee. The push was enabled by executive orders signed by Trump that seek to speed up permitting and development timelines for AI data centers.

Would the Fort Bliss data center pay taxes?

A privately-financed data center on Fort Bliss would likely have to pay some taxes – unlike on-base government facilities – but there’s a lot of uncertainty.

Carlyle Group is leasing the land for the data center under an “enhanced use lease” that allows branches of the military to rent under-used land on bases.

Land on federal installations is not subject to state or local taxes. However, the statute that authorizes the U.S. military to lease excess land to private entities says that “the interest of a lessee of property leased under this section may be taxed by State or local governments.”

So, while the land the data center is built on would not be subject to taxation, the structures housing the data center could be subject to local property taxes.

But it depends on how the deal is structured, including factors such as whether Carlyle or the Army ultimately takes ownership of the buildings.

The Army in January awarded a contract to Korean-owned Hanwha Defense USA, which will invest $1.3 billion to develop a munitions factory at a base in Pine Bluff, Arkansas, using an enhanced use lease.

Fitzgerald, the Army undersecretary, acknowledged the public pushback to other data centers such as Meta and Project Jupiter. But he said the Army wants to ensure the project is developed “the right way.”

“There are always elements that will kind of make this an ‘us versus them’ sort of a construct, but I don’t think we view it that way from the Army,” he said. “I think there’s a path here that will benefit not just the installation, but the community as well.”

Texas could lose nearly $8 billion in revenue from 2026 to 2030 due to data center tax exemptions, according to The Texas Tribune. Photo via Pexels

Houston lawmaker may kill data center tax breaks due to $8B revenue loss

looking at the data

An influential Houston-area state senator is raising concerns about potentially billions of dollars in lost state revenue from tax breaks for Texas data centers—and is pondering legislation that would abolish the tax incentives.

Citing data from the state comptroller’s office, The Texas Tribune reports the state stands to lose nearly $8 billion in revenue from 2026 to 2030 due to sales tax and use tax exemptions for data centers. During the state’s 2025 fiscal year, which ended on Aug. 31, these tax exemptions caused Texas to lose a little over $1 billion, up from an earlier estimate of $130 million.

“These new numbers are extremely concerning, and I will say they’re unsustainable,” Republican state Sen. Joan Huffman, chairwoman of the state Senate Finance Committee, tells The Texas Tribune. “I plan to look at filing legislation to either repeal the exemption or take a very close look at it and see.”

Texas on track to be No. 1 data center market in U.S.

Scrutiny of the tax breaks comes amid an explosion of data center development in Texas, where data provider Aterio identifies nearly 1,000 centers that are operating, under construction or planned.

A report issued in January by Bloom Energy says the state is poised to become the No. 1 U.S. market for data centers within three years. By 2028, according to the report, Texas is projected to exceed 40 gigawatts of data center capacity—representing nearly 30 percent of total U.S. demand.

Among companies benefiting from the data center boom are:

  • Tech titans like Apple, Google, Meta Platforms, and Microsoft, which are spending billions of dollars to build data centers in Texas.
  • Spring-based ExxonMobil and Houston-based Chevron, two oil and energy giants that are developing natural gas plants to supply power for data centers.
  • Houston-based energy technology company Baker Hughes, which is collaborating with Google Cloud to develop AI-enabled power optimization and sustainability software for data centers.
  • DataBank, Data Foundry, Equinix, Digital Realty, Lumen Technologies, and IBM, all of which operate data centers in the Houston area.

The Texas Legislature will begin debating tax breaks for data centers in July, when Huffman’s Senate Finance Committee meets for an interim hearing before the 2027 legislative session, according to the Tribune.

Data center industry defends tax breaks

Leaders in the data center industry warn that watering down or halting the tax breaks could slow down or even end Texas’ ascent in the data center sector.

A 2025 report commissioned by the Data Center Coalition found that in 2024, data centers provided more than $1.6 billion in state tax revenue and almost $1.6 billion in local tax revenue in Texas. Over the next several years, according to the report, planned development of data centers in the Lone Star State could generate almost $3.8 billion in state tax revenue and more than $4.9 billion in local tax revenue.

In 2024, the Houston area had 8.1 million gross square feet of data centers, with the properties’ real estate investments sitting at $10 billion, according to the report. That year, data centers in the region produced a little over $700 million in state and local tax revenue. About 60 data centers operate in the Houston area.

Watchdog group warns of tax breaks’ danger to state budgets

On the other side of the debate over tax breaks for data centers, a report released last year by Good Jobs First, a nonprofit, nonpartisan watchdog group that tracks economic development incentives, decries the tax breaks as dangerous to state budgets.

“We know of no other form of state spending that is so out of control. Therefore, we recommend that states cancel their data center tax exemptions,” says Good Jobs research analyst Kasia Tarczynska, co-author of the report. “Shy of that, states should amend … legislation to cap how much any facility and company can avoid paying in taxes each year.”

Chevron is in talks with Microsoft and Engine No. 1 about a massive natural gas power plant in Texas. Photo via Getty Images

Chevron eyes $7B Texas power plant for Microsoft data center campus

power deal

Software giant Microsoft is negotiating exclusively with Houston-based oil and gas titan Chevron and investment firm Engine No. 1 about the development of a $7 billion power plant in West Texas that would supply electricity for a Microsoft data center campus.

The proposed natural-gas-fired plant initially would generate 2,500 megawatts of electricity, Bloomberg reports. The plant would be built near Pecos, a Permian Basin city, in an area where Microsoft plans to build a 2,500-megawatt data center campus on a 7,000-acre site.

A deal with Microsoft would secure a long-term customer for the plant’s output and help finance its construction, Bloomberg says. The project, expected to be producing power by 2030, still requires tax and environmental approvals as well an agreement to terms among Chevron, Engine No. 1, and Microsoft.

In a statement issued after Bloomberg reported the news, Chevron acknowledged it was in exclusive talks with Engine No. 1 and Microsoft, but the oil and gas company offered no details.

Chevron says the proposed plant “reflects an emerging shift in how power for AI is being developed, bringing energy supply closer to demand through co-located, behind-the-meter generation to deliver reliability while helping avoid added strain on regional electricity systems. It pairs sustained, always-on demand from advanced computing with proven capability to design, build, and operate large-scale energy infrastructure.”

Development of gas-powered electrical plants for AI data centers represents a new—and potentially lucrative— business line for Chevron. In 2025, Chevron, Engine No. 1 and GE Vernova announced a partnership to produce natural gas for AI data centers in the U.S.

Chevron’s collaboration with Engine No. 1 has already secured an order for seven large natural gas turbines from GE Vernova, according to Bloomberg.

“Energy is the key to America’s AI dominance,” Chris James, founder and chief investment officer of Engine No. 1, said last year. “By using abundant domestic natural gas to generate electricity directly connected to data centers, we can secure AI leadership, drive productivity gains across our economy, and restore America’s standing as an industrial superpower.”

Houston's data center scene has received its latest bullish forecast. Photo via serverfarmllc.com

Houston data center capacity could more than double by 2028, CBRE report says

data analysis

The Houston market could more than double its data center capacity by the end of 2028, a new report indicates.

The report, published by commercial real estate services provider CBRE, says greater demand for data center capacity in the Houston area is being fueled by energy companies, along with large-scale cloud services and AI-driven tenants.

In the second half of 2025, the Houston market had 154 megawatts of data center capacity, which was on par with capacity in the second half of 2024. Another 28.5 megawatts of capacity was under construction during that period.

“Multiple providers are advancing new builds and redevelopments, including significant power upgrades to recently purchased buildings, underscoring long-term confidence even as the market works through elevated vacancy and uneven absorption,” CBRE says of Houston’s data center presence.

One project alone promises to significantly boost the Houston market’s data center capacity. Data center developer Serverfarm plans to use part of a $3 billion credit facility to build a 250-acre, AI-ready data center campus near Houston with a potential capacity of more than 500 megawatts. The Houston campus and two other Serverfarm projects are already leased to unidentified tenants, according to CoStar.

A 60-megawatt, AI-ready Serverfarm data center is under construction in Houston. The $137 million, 438,000-square-foot project, located near the former headquarters of computer manufacturer Compaq, is supposed to be completed in the third quarter of 2027.

Data Center Map identifies 59 data centers in the Houston area managed by 36 operators, including DataBank, Data Foundry, Digital Realty, IBM, Logix Fiber Networks, Lumen and TRG Datacenters. That compares with more than 180 data centers in Dallas-Fort Worth, more than 50 in the San Antonio area and 40 in the Austin area.

Texas is home to more than 400 data centers, according to Data Center Map.

In November, Google said it’s investing $40 billion to build AI data centers in West Texas and the Texas Panhandle.

“This is a Texas-sized investment in the future of our great state,” Gov. Greg Abbott said when Google’s commitment was announced. “Texas is the epicenter of AI development, where companies can pair innovation with expanding energy. Google's $40 billion investment makes Texas Google's largest investment in any state in the country and supports energy efficiency and workforce development in our state.”

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Buoyed by $1.3B sales backlog, microgrid company ERock files for IPO

eyeing ipo

Another energy company in Houston is going public amid a flurry of energy IPOs.

Houston-based ERock Inc., which specializes in utility-grade onsite microgrid systems for data centers and other customers, has filed paperwork with the U.S. Securities and Exchange Commission (SEC) to sell its shares on the New York Stock Exchange.

The ERock filing follows the recent $1.9 billion IPO of Houston-based Fervo Energy, a provider of geothermal power that’s now valued at $7.7 billion.

Another Houston energy company, EagleRock Land, just went public in a $320 million IPO that values the company at $3 billion. EagleRock owns or controls about 236,000 acres in the Permian Basin, earning money from royalties, fees, easements, water services and other revenue streams tied to drilling on its land.

According to Barron’s, more than a dozen energy and energy-related companies in the U.S. have gone public since the beginning of 2025, with the bulk of the IPOs happening this year.

ERock’s SEC filing doesn’t identify the per-share pricing range for the IPO or the number of Class A shares to be offered. ERock is a portfolio company of Energy Impact Partners, a New York City-based venture capital and private equity firm that invests in energy companies.

The company previously did business as Enchanted Rock. ERock Inc., formed in January, will function as a holding company that controls predecessor company ER Holdings Ltd.

In 2025, ERock generated revenue of $183.1 million, up 42.5 percent from the previous year, according to the IPO filing. It recorded a net loss of $59 million last year.

As of March 31, ERock boasted a sales backlog of nearly $1.3 billion, up 779 percent on a year-over-year basis. The company attributes most of that increase to greater demand from data centers.

The company primarily serves the power needs of data centers, utilities, industrial facilities, and commercial buildings. Its biggest markets are Texas and California.

“Several U.S. markets, such as Texas and California, face especially acute reliability risks,” ERock says in the SEC filing. “Texas already shows rapid load-growth pressures tied to data centers and industrial expansion, while California faces grid congestion, long interconnection queues, and above-average vulnerability to extreme heat- and weather-driven outages.”

Since its founding in 2018, ERock has installed microgrid systems at more than 400 sites with a capacity of about 1,000 megawatts. Customers include ComEd, Foxconn, H-E-B, Microsoft and Walmart.

By the end of this year, the company plans to expand its production of microgrid systems to a capacity of about 1.2 gigawatts with the opening of its Hyperion facility in Houston.

John Carrington leads ERock as CEO. He joined ER Holdings last year as chairman and CEO. Carrington previously was CEO of Houston-based Stem, a public company that offers AI-enabled clean energy software and services. Earlier, he spent 16 years at General Electric.

Houston investment firm closes $105M energy venture fund

seeing green

Houston-based investment firm Veriten has announced the initial close of its second flagship energy venture fund with more than $105 million in capital commitments.

Fund II will build on Veriten’s initial fund and aim to support “scalable technology solutions for energy, power and industrial applications,” according to a company news release.

"Our differentiated network, research-driven process, and first principles approach to investing are having an impact across multiple verticals including traditional energy, electrification, and industrial technology. Fund II builds on that platform,” John Sommers, partner, investments at Veriten, added in the release. “In this environment, the differentiator isn't capital – it's all about connectivity, deep sector expertise, and an economically-driven approach. As new technologies and approaches develop at breakneck speed, the need for more reliable, affordable energy and power continues to grow dramatically. The current backdrop accentuates the need for Veriten's solution."

Veriten is supported by over 50 strategic partnerships in the energy, power, industrial and technology sectors, including major players like Halliburton and Phillips 66.

"Veriten continues to build a differentiated platform at the intersection of energy, technology and industry expertise," Jeff Miller, chairman and CEO of Halliburton, said in the release. "We were early believers in the team and their ability to identify practical solutions to real challenges across the energy value chain. As all industries increasingly adopt digital tools, automation and AI-enabled technologies to improve performance and execution, we are proud to partner with Veriten again to help accelerate high-impact solutions across the broader energy landscape."

Veriten closed its debut fund, NexTen LP, of $85 million in committed capital in October 2023. It was launched in January 2022 by Maynard Holt, co-founder and former CEO of the energy investment bank Tudor, Pickering, Holt & Co.

It has invested in Houston-based AI-powered electricity analytics provider Amperon and led a $12 million Seed 2 funding round for Houston-based Helix Technologies to scale manufacturing of its energy-efficient commercial HVAC add-on earlier this year. In the past year it has contributed to funding rounds for San Francisco-based Armada and Calgary-based Veerum.

Veriten also named Nick Morriss as its new managing director earlier this month. Morriss most recently served as vice president of business development at next-generation nuclear technology company Natura Resources and spent nearly 20 years at NOV Inc.

Texas solar set to overtake coal for first time in 2026, EIA forecasts

solar on the rise

Solar power promises to shine even brighter in Texas this year.

A new forecast from the U.S. Energy Information Administration (EIA) indicates that for the first time, annual power generation from utility-scale solar will surpass annual power generation from coal across the territory covered by the Electric Reliability Council of Texas (ERCOT).

Solar generation is expected to reach 78 billion kilowatt-hours in 2026 in the ERCOT grid, compared with 60 billion kilowatt-hours for coal, the EIA forecast says. The ERCOT grid supplies power to about 90 percent of Texas, including the Houston area.

“Utility-scale solar generation has been increasing steadily in ERCOT as solar capacity additions help meet rapid electricity demand growth,” the forecast says.

Although natural gas remains the dominant source of electricity generation in ERCOT, accounting for an average 44 percent of electricity generation from 2021 to 2025, solar’s share of the generation mix rose from four percent to 12 percent. During the same period, coal’s share dropped from 19 percent to 13 percent.

EIA predicts about 40 percent of U.S. solar capacity, or 14 billion kilowatt-hours, added in 2026 will come from Texas.

Although EIA expects annual solar generation to exceed annual coal generation in 2026, solar surpassed coal in ERCOT on a monthly basis for the first time in March 2025, when solar generation totaled 4.33 billion kilowatt-hours and coal’s totaled 4.16 billion kilowatt-hours. Solar generation continued to exceed that of coal until August of that year.

“In 2026, we estimate that solar exceeded coal for the first time in March, and we forecast generation from solar installations in ERCOT will continue to exceed that from coal until December, when coal generation exceeds solar,” says EIA. “We expect solar generation to exceed that of coal for every month in 2027 except January and December.”

For 2027, EIA forecasts annual solar generation of 99 billion kilowatt-hours in the ERCOT grid, compared with 66 billion kilowatt-hours of annual coal generation.

In April, ERCOT projected almost 368 billion kilowatt-hours of demand in ERCOT’s territory by 2032. ERCOT’s all-time peak demand hit 85.5 billion kilowatt-hours in August 2023.

“Texas is experiencing exceptional growth and development, which is reshaping how large load demand is identified, verified, and incorporated into long-term planning,” ERCOT President and CEO Pablo Vegas said. “As a result of a changing landscape, we believe this forecast to be higher than expected … load growth.”