The report concludes that natural gas would need to remain a “foundational component of the region’s energy system” to meet the demands of AI data centers. Photo courtesy UH

A new study from the University of Houston estimates that the U.S. will need more than $1 trillion in new midstream energy infrastructure investment by 2052 to meet the rising energy demands from data centers in the age of artificial intelligence.

According to the report, this would average $40 billion to $48 billion per year across investments in natural gas, oil, natural gas liquids, hydrogen and CO2 infrastructure.

UH, in collaboration with the INGAA Foundation and Wood and ESMIA Consultants, released the 2025 North American Midstream Infrastructure Report, which details the needs, pipelines and associated infrastructure necessary to meet global market needs and increased energy demands. UH led the consortium that conducted the analysis. Paul Doucette, hydrogen program officer at UH, served as the principal investigator of the report.

According to the U.S. Department of Energy, data center energy consumption could reach 800 terawatt-hours annually by 2050, a roughly 167 percent increase from 300 terawatt-hours in 2025. Meanwhile, electricity generation from all energy sources is projected to reach 5,858 terawatt-hours in 2052, a 27 percent increase over current levels.

The report proposes two routes to meeting this level of demand.

The first scenario is a reference case based on current federal, state and provincial policies as of April 1, 2025. The second option presents a low-carbon scenario. The report concludes that natural gas would need to remain a “foundational component of the region’s energy system” in both scenarios.

“Meeting energy demand is a critical challenge right now, and this report quantifies the necessary midstream infrastructure and corresponding development dollars needed to meet that demand,” Hebe Shaw, executive director of the INGAA Foundation, said in a news release. “Meeting the energy needs of North America will require sustained investment and development, which must begin now to ensure a safe, reliable and affordable energy system.”

The report also identified several key midstream infrastructure requirements, including:

  • 103,000 miles of new natural gas gathering pipelines
  • 37,000 miles of additional natural gas transmission pipelines, which includes approximately 33,800 miles in the United States
  • 24 million jobs over 25 years

The report adds that hydrogen, carbon capture, utilization, and storage (CCUS), and other decarbonization strategies can help meet infrastructure needs.

UH released a condensed version of the report here.

Chevron will power the forthcoming Project Kilby using natural gas. Photo via Getty Images

Chevron inks 20-year deal to power massive Microsoft data center in West Texas

power deal

Chevron and Microsoft have signed a 20-year deal in which Chevron will provide natural-gas-fired power for a future West Texas data center, known as Project Kilby.

The proposed Microsoft data center could be one of the biggest in the U.S. and is expected to deliver 2.67 gigawatts of capacity. It will be built through a “phased, modular approach that enables incremental expansion over time,” according to Chevron.

Chevron expects the facility to be up and running by 2028, though the company won’t make a final investment decision on the project until later this year. The company is collaborating on Project Kilby with investment fund Engine No.1.

Project Kilby is projected to bring in $10 billion in state and local tax revenue and support 2,000 jobs, according to Chevron. The plant will use non-potable, brackish groundwater for power plant operations and aims to find new ways to reuse water produced by oil and gas operations.

The site will use selective catalytic reduction systems to reduce nitrogen oxide emissions and minimize noise and light impacts and will utilize other advanced air emissions control technologies. A majority of the generation will come from large turbines developed by Chevron partner GE Verona with additional capacity from Caterpillar’s solar turbines. The plant will be fed by natural gas from the Permian Basin.

“Chevron is uniquely positioned to deliver power to customers with certainty, speed and at a competitive cost, leveraging Permian natural gas and our proven execution capabilities,” Jeff Gustavson, Chevron president of new energies, said in a news release. “This project links Chevron’s traditional strengths to emerging demand, creating differentiated value for our shareholders and the communities where we operate.”

According to BloombergNEF, the U.S. is expected to increase its data center capacity to 77 gigawatts by 2030. Another report from Bloom Energy predicts Texas will see a 142 percent increase in its market share for data centers from 2025 to 2028.

“The rapid growth we’re experiencing in AI and cloud, driven by customer demand, requires energy infrastructure that can scale quickly and reliably,” Noelle Walsh, Microsoft president of cloud operations and innovation, added in the news release. “Our agreement with Chevron helps ensure we’ll have dedicated, large-scale power to support the evolution and reliability of advanced computers. Through this partnership, we’re delighted to grow with and become a deeper part of the West Texas community.”

Chevron was named No. 21 on the 2026 Fortune 500 list earlier this month.

Texas is poised to become the world’s largest data center market. Photo courtesy Google

Texas Gov. Abbott seeks data center crackdown as state grapples with growing power demand

growing pains

Just seven months ago, Gov. Greg Abbott trumpeted Google’s $40 billion plan to add three data center campuses in Texas. Now, amid growing public outcry over such projects, Abbott is pushing for a regulatory crackdown on data centers in the Lone Star State.

Abbott recently sent a letter to leaders of the Public Utility Commission of Texas (PUC) and the Electric Reliability Council of Texas (ERCOT) proposing stricter oversight of the state’s data centers. Texas is home to more than 400 data centers, with many more on the way, and is poised to become the world’s largest data center market.

Among other things, Abbott wants to:

  • Ensure residential electric bills go down — not up — as data centers connect to ERCOT’s grid, which supplies power for about 90 percent of Texans.
  • Require data centers to cover the costs of upgrades to deliver electricity to the power-hungry facilities.
  • Repeal sales tax exemptions and other “outdated or unnecessary” financial incentives for data centers.
  • Institute “best practices,” such as property setbacks and noise-reduction technology, to ease the impact of data centers on nearby residents.
  • Demand that all new data centers, which use a tremendous amount of water, be built with water-efficient technology.
  • Require large data centers to generate annual reports on their use of electricity and water.

Abbott has set a July 17 deadline for the PUC and ERCOT to address his recommendations.

“As Texas continues to welcome innovation and investment, we must ensure that growth strengthens our people and their quality of life without placing undue burdens on Texans and local communities,” Abbott wrote.

Abbott’s call for tighter control of data centers has elicited both praise and skepticism.

In a social media post on X, Texas House Speaker Dustin Burrows, a Lubbock Republican, thanked Abbott for seeking “accountability and reform” in the state’s data center industry. Burrows has made data centers one of his priority issues for the 2027 state legislative session.

State oil and gas regulator Wayne Christian, a member of the Texas Railroad Commission, weighed in with similarly positive comments about Abbott’s directive. He says an outright ban on data centers isn’t the answer to residents’ complaints about new facilities.

“The Texas way is not to answer innovation with government overreach or fear-driven bans,” Christian, whose agency wasn’t cited in Abbott’s letter, said in a statement posted on X. “Our job is to protect prosperity, safeguard taxpayers and ensure the infrastructure that powers our economy remains strong and reliable.”

Gina Hinojosa, an Austin Democrat who’s challenging Abbott in this November’s gubernatorial race, took issue with the governor’s edict on data centers.

“Greg Abbott is changing his tune on data centers because he knows his policies are unpopular,” Hinojosa, a state representative, wrote on X. “Nobody believes the arsonist is gonna be the one to put out the fire.”

Abbott’s call for stepped-up regulation of data centers echoes many of the concerns expressed by the state chapter of the Sierra Club, an environmental nonprofit.

“The growth of data centers reflects a broader transformation taking place across Texas,” the Sierra Club says on its website. “The state is becoming a hub for the technologies that will shape the future economy, from artificial intelligence to advanced computing and cloud services. At the same time, Texans deserve transparency about how these projects affect the communities where they are built.”

Houstonians are concerned about data centers' high energy demands and the area’s power grid reliability, according to a new report. Photo courtesy UH

New survey reveals concerns over AI data center growth in Houston

data findings

A new report out of the University of Houston shows that area residents remain wary of the long-term effects of operating data centers.

The recent survey from the University of Houston’s latest SPACE City Panel, conducted by the Center for Public Policy at the Hobby School of Public Affairs, shows that while 85 percent of Houston-area residents use AI, nearly 63 percent oppose the construction of AI data centers within 1 mile of their homes.

Respondents’ concerns centered around data centers’ high energy demand and the area’s power grid reliability. According to the survey, 32 percent of residents who oppose local data center projects would be more likely to support the centers if they relied on renewable energy over fossil fuels.

“Respondents understand that AI can bring economic and educational benefits, but they are also concerned about the physical infrastructure needed to fuel AI, especially data centers,” Soran Mohtadi, post-doctoral fellow at the Hobby School and a researcher on the report, said in a news release. “This physical infrastructure demands more electricity and water, leading to environmental impacts.”

Experts estimate that 6.5 gigawatts of data center capacity will be added to the Texas grid by 2030. And Houston’s data center capacity is predicted to more than double by 2028.

The Electric Reliability Council of Texas also projects electricity demand could reach 218 gigawatts by 2031, which would be more than double the record peak set in August 2023. Data centers are expected to account for 86 gigawatts of that new demand.

Survey respondents also said they are concerned about the state's future water supply, given the large amounts of water that data centers need to stay cool.

In terms of who’s responsible for that issue, 57.6 percent of respondents said they put the onus on Texas lawmakers, while 31.5 percent say tech companies should be responsible.

Additionally, more than 75 percent of respondents believed that data center developers and technology companies—not residents—should bear the cost of infrastructure upgrades to support data centers.

“Every decision legislators make has implications on residents’ everyday lives and local infrastructure now and in the future,” Maria P. Perez Arguelles, lead researcher on the report and research assistant professor at the Hobby School, added in the news release. “This issue is going to become more important in years to come, so this is just the beginning.”

Read the full report here.

---

This article originally appeared on our sister site, EnergyCapitalHTX.com.

Corpus Christi, Texas is already facing prolonged drought and water concerns. Photo by Brandon Bell/Getty Images

New Texas water plan does not consider data center growth, critics say

For the Future

A draft of Texas’ 2027 State Water Plan is drawing concerns from some water protection advocates who say it fails to account for one growing industry: data centers.

The plan, created by the Texas Water Development Board, will guide tens of billions of dollars in water development projects over the coming decades.

On Memorial Day, people packed Lake Travis to enjoy the water and sunshine while the lake remains near full capacity. But some advocates warn drought conditions could quickly return.

“Once we get into August, September, we'll be probably right back in the same drought situation,” said Mike Clifford with the Greater Edwards Aquifer Alliance.

The Texas Water Development Board released the draft plan in April. It recommends thousands of water projects carrying a projected cost of $174 billion over 50 years.

“We're not as shocked about the dollar amounts as some people are,” Clifford said. "To secure our water future, that's not an insane amount to ask for."

However, Clifford said his organization was surprised the draft does not specifically account for the growing impact of data centers, which can consume large amounts of water.

“If you leave the data centers out, it's not really a plan in our opinion. It's going to have to be changed and it's going to fall short,” Clifford said.

According to Data Center Map, Texas is currently home to 461 data centers.

Clifford argues the state should use projected future growth, not just historical data, when planning for long-term water needs.

“They're looking at the previous 10 years or 20 years or whatever, and we didn't have a lot of data centers in Texas,” he said.

Researchers at the the University of Texas at Austin estimate data centers could account for as much as 9 percent of Texas’ total water use by 2040, or potentially surpass the oil and gas industry that same year.

--

Read the full story from CultureMap news partner KVUE.com.

Scotty Nyquist discuss the growth in AI data centers and the strain on the system. Photo via HARC report

Houston energy expert asks: Who pays when AI outruns the power grid?

Guets Column

For most of the past 20 years, U.S. electricity policy relied on predictable trends in demand. Electricity use, in most regions, increased gradually, forecasts were stable, and utilities adjusted the system in small steps. Power plants, transmission lines, and substations were generally added to reflect shifts in load, rather than growth, and costs were recovered through modest adjustments to customer bills.

Growth in AI data centers has disrupted this model. A single facility can add as much electricity demand as a small town. That demand comes all at once, runs continuously, and has little tolerance for outages. If electricity service drops even briefly, computation stops, and services shut down. Ironically, data centers need reliable service, a point that their emergence is driving concern around for the rest of the grid.

What the numbers say

The International Energy Agency projects global electricity consumption from data centers to double by 2030, reaching roughly 945 TWh, nearly 3 percent of global electricity demand, with consumption growing about 15 percent per year this decade. McKinsey projects that U.S. data center demand alone could grow 20–25 percent per year, with global capacity demand more than tripling by 2030.

After years of roughly 0.5 percent annual demand growth, many forecasts now place total U.S. electricity demand growth closer to 2–3 percent per year through the mid-2030s, with much higher growth in specific regions. In Texas, some forecasters are saying electricity demand could double over the next five years, a staggering 10 percent per year growth rate. What sounds incremental on paper translates into a major challenge on the ground. Meeting this pace of growth is estimated to require $250–$300 billion per year in grid investment, about double what the system has been absorbing.

Where the system starts to strain

The strain appears first in the interconnection queue. It shows up as long waits, backlogs, and delays for connecting new loads and new generation.

Before new generators or large load customers can be connected, a study is required to assess their impact on the grid, whether it can physically handle the added load, and whether upgrades are required. With AI-driven data centers, utilities face far more connection requests than they can realistically support. In ERCOT, large-load interconnection requests exceed 200 gigawatts, most tied to data centers. That amount exceeds historical norms, and it is several times larger than what can be practically studied or built in the near term.

To be clear, public utility commissions are required to study these requests because they must manage system capabilities to ensure minimal disruption. This means engineers spend time evaluating projects that may never be built, while other more commercially viable projects may wait longer for approvals. This extends timelines and makes infrastructure planning less reliable.

Why policymakers are rethinking the rules

Utilities and their regulators must decide how much generation, transmission, and substation capacity to build years before it comes online. Those decisions are based on expected demand at the time projects are approved. When it comes to data centers, by the time infrastructure is completed, they may end up deploying newer, more efficient chips that use less power than originally assumed. This can result in grid infrastructure built for a higher load than what actually materializes, leaving excess capacity that still must be paid for through system-wide rates.

That’s the central dilemma. If utilities build too little capacity, the system operates with less reserve margin. During periods of grid stress, operators have fewer options, increasing the likelihood of curtailments or outages. However, if utilities build too much, customers may be asked to pay for infrastructure that is not fully used.

In response, policymakers are adjusting the rules. In some regions, regulators are moving toward bring-your-own-power approaches that require large data centers to supply or fund part of the capacity needed to serve them or reduce demand during system stress. At the federal level, permitting reforms tied to datacenter infrastructure increasingly treat electricity as a strategic economic input.

As Ken Medlock, senior director at the Baker Institute Center for Energy Studies (CES), explains:

“Many of the planned data centers are now also adding behind-the-meter options to their development plans because they do not anticipate being able to manage their needs solely from the grid, and they certainly cannot do so with only intermittent power sources.”

Behind-the-meter (BTM) refers to power that a consumer controls on its side of the utility meter, such as on-site gas generation or a dedicated power plant. These resources allow data centers to keep operating during grid-related service. Most facilities remain connected to the grid, but the backup BTM generation serves as insurance for operating their core business.

This shifts responsibility. Utilities traditionally manage reliability across all customers by maintaining an operating reserve margin, or spare capacity. Increasingly, large-load customers manage part of their own electricity reliability needs, which changes how infrastructure is planned and how risk is distributed.

Bottom line

AI-driven load growth is arriving faster and in more concentrated places than the power system was built to accommodate. Utilities and regulators are being forced to make decisions sooner than planned about where to build, how fast to build, and which customers get priority when capacity is limited. The effects extend beyond data centers, showing up in system costs, reliability margins, competition for grid access, and pressure on communities and industries that depend on affordable and dependable power. The issue is not whether electricity can be generated, but how the costs and risks of rapid demand growth are distributed as the system tries to keep up. How regulators balance these decisions will determine who pays as AI demand outruns the power grid.

-----------

Scott Nyquist is a senior advisor at McKinsey & Company and vice chairman, Houston Energy Transition Initiative of the Greater Houston Partnership. The views expressed herein are Nyquist's own and not those of McKinsey & Company or of the Greater Houston Partnership. This article originally appeared on LinkedIn.

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Texas City ammonia plant acquired by Yara in $1.3 billion deal

Ammonia Acquisition

Yara North America, a subsidiary of Norwegian fertilizer and ammonia producer Yara International, has agreed to buy an ammonia production plant in Texas City for $1.3 billion.

The seller is GCA Holdings, an affiliate of Texas City-based chemical manufacturer Gulf Coast Ammonia, which is owned by private equity firms Lotus Infrastructure Partners and MB Energy.

The Texas City plant, with an eventual annual capacity of 1.3 million metric tons, is expected to start full production by the end of this year. Yara says the ammonia produced by the plant will serve its own fertilizer production system and its key customers.

During a recent call with analysts and investors, Magnus Ankarstrand, executive vice president and CFO of Yara International, said the plant holds the potential to become one of the company’s most profitable plants. The $1.3 billion purchase price, he added, “is a very attractive entry ticket to ammonia production in the U.S. at a very attractive cost.”

The Texas City plant will add to Yara’s holdings in the Lone Star State, as Yara is the majority owner of an ammonia, hydrogen and nitrogen production plant in Freeport.

Construction of the ammonia plant began in 2020, but technical and infrastructure issues delayed the project. On its website, Gulf Coast Ammonia says the plant represented a $600 million investment.

“Gulf Coast Ammonia is a world-class asset that required disciplined execution across development, financing, construction, and commercial structuring,” Philipp Pletka, managing director of Lotus Infrastructure Partners, says in a news release.

Trexlertown, Pennsylvania-based Air Products, which owns and operates the country’s largest hydrogen pipeline network, will continue to supply hydrogen and nitrogen for the plant under a long-term deal with Yara, according to the release.

However, the news comes two days after Yara International announced that it would no longer be purchasing ammonia assets in the Louisiana Clean Energy Complex (LCEC) from Air Products. In a separate release, Yara said it planned to reallocate funds toward "alternative mature U.S. ammonia investment opportunities with more competitive returns."

Houston hypersonic engine company lands $91M to accelerate production

Clean Speed

Houston-based Venus Aerospace has closed a $91 million Series B round and plans to scale the production of its hypersonic engine.

The round was led by Houston-based Mercury Fund with participation from Lockheed Martin Ventures, MESH, PEAK6, Draper Associates, Starboard Star Venture Capital, Green Sands Equity and other investors, according to a news release.

The investment comes about a year after Venus completed the first U.S. flight test of its high-thrust rotating detonation rocket engine (RDRE). The engine is expected to enable vehicles to travel four to six times the speed of sound from a conventional runway and is about 15 percent more efficient than traditional alternatives, according to the company.

Venus Aerospace says the latest round of funding will allow it to move the RDRE from demonstration to deployment and meet customer requirements for the near-term defense and space industries. The company says that the reusable RDRE is designed with a "common propulsion architecture" that can work for multiple industries and mission types.

“This financing marks an important step in moving Venus from breakthrough demonstration to scaled capability,” Sassie Duggleby, co-founder and CEO, said in the news release. “Our customers need propulsion systems that go farther, can be produced reliably and are built on supply chains they can trust. We are advancing that capability with American engineering and manufacturing talent to strengthen U.S. defense, expand space access and support the future of high-speed flight.”

Venus Aerospace raised a $20 million Series A in 2022, led by Wyoming-based Prime Movers Lab. At the time, the company said it would put the funding toward three main technologies: a next-generation rocket engine, aircraft shape and leading-edge cooling system.

The company also picked up an investment from Lockheed Martin Ventures, the investment arm of aerospace and defense contractor Lockheed Martin, in November 2025—in addition to funding from other investors over the years.

“Since our initial investment, Venus has progressed very quickly in its technology development," Chris Moran, vice president and general manager of Lockheed Martin Ventures, added in the release. "Our reinvestment in Venus recognizes Venus’ accomplishments to date and focus on speed to manufacture, cost management and reduction of supply chain constraints. Venus is working effectively to position its propulsion system for the production scale required by defense programs.”

"Venus is exactly the kind of company Houston capital should be backing," Blair Garrou, co-founder and managing partner at Mercury Fund, added in the release. "It combines multiple frontier technologies, domestic manufacturing and clear commercial and national security relevance. We believe this team is positioned to lead an important new chapter in defense and space, and we are proud to support a company building breakthrough technology here in Texas."

Venus Aerospace and Houston clean tech startup Vaulted Deep were also named to the World Economic Forum's Technology Pioneers community earlier this summer.

---

This article first appeared on InnovationMap.com.

14 climatech startups join Greentown Houston in first half of 2026

green team

Climatech incubator Greentown Labs reports that 14 startups have joined its Houston community so far this year.

The companies are among 30 new startups to have joined Greentown Houston and Greentown Boston in 2026. Four of the companies are headquartered in Houston.

The startups are working on a range of "hydrogen-powered heavy-duty transport to AI-driven grid interconnection," according to Greentown.

The local startups that joined Greentown Houston include:

  • Houston-based Focis AI, which transforms industrial laser scans into structured asset intelligence to automatically identify, classify and map components in refineries and plants
  • Houston-based Iron Lattice, which develops next-generation memory technology for AI and high-performance computing that improves energy efficiency, endurance and scalability while remaining compatible with existing semiconductor manufacturing
  • Houston-based Orbital Arc, which is developing a new ion engine designed to improve the efficiency and scalability of spacecraft propulsion from low Earth orbit to deep space
  • Houston-based Sustain Energy LLC, which delivers cleaner, lower-cost fuel to industrial customers in pipeline-absent, underserved markets, cutting their energy costs and emissions with no infrastructure investment on their end

Other startups from around the world joined the Houston incubator in the same time period, including:

  • Ankara-based AIS Field, which develops robotic, AI-assisted non-destructive inspection systems, including submersible tank and boiler crawlers
  • San Francisco-based Armada AI, which builds rapidly deployable modular and edge data centers that run on local, stranded, or renewable power
  • San Francisco-based Armeta, which turns complex engineering drawings and legacy documentation into structured, usable data
  • Pittsburgh-based Atlas Robotics, which develops a Physical AI platform that powers autonomous material-handling robots and AI-guided forklifts
  • Ghana-based Cocoa Potash, which transforms high-emissions agricultural waste from cocoa, coconut, and palm-nut into organic potash, fertilizer and renewable energy
  • Israel-based Criaterra, which produces low-carbon, cement-free building materials
  • Italy-based ETAK, which manufactures modular reactors that convert solid waste into clean syngas
  • Kenya-based FelixFusion, which uses its Felix platform to model every grid connection point, including capacity, upgrade costs, and constraints
  • San Diego-based Gemini Energy, which builds next-generation fuel cells for data-center power
  • Tokyo-based Hibot, which develops robotic systems for inspecting and maintaining infrastructure in hazardous, hard-to-access environments
  • Austin-based Sheetak, which designs and manufactures thermoelectric coolers, generators, and assemblies for solid-state cooling and energy harvesting
  • The Netherlands-based ToPerform, which makes AI-powered, non-intrusive fouling sensors that monitor pipelines around the clock and predict the optimal cleaning time

Another 16 startups joined Greentown's Boston incubator. See the full list of new members here.

More than 100 startups joined Greentown last year, according to an end-of-year reflection shared by Greentown CEO Georgina Campbell Flatter. Read more about them here.