ai alliance

SLB teams with Liberty Energy on modular power for AI data centers

SLB and Liberty Energy are working together to help solve the "bottleneck in AI infrastructure." Image courtesy SLB

Houston-headquartered SLB and Denver-based Liberty Energy Inc. announced a strategic agreement this month to support the rapid growth of new data center capacity.

Under the agreement, SLB will supply modular data center infrastructure and oversee large-scale execution, while Liberty will provide modular power generation systems and behind-the-meter power management technology for developers looking to add capacity. According to Reuters, the power will come from natural gas generation.

“The bottleneck in AI infrastructure is no longer just compute. It is the ability to deliver infrastructure and power on the timelines the market now demands,” Gavin Rennick, president of SLB’s New Energy and Industrial business, said in a news release. “By bringing together complementary infrastructure and power capabilities, we will help developers accelerate deployment of new data center capacity.”

The companies seek to specifically offer the modular technologies in areas without traditional grid connections or where grid capacity is limited.

They also aim to improve the "efficiency, flexibility and environmental performance of future data center energy systems," potentially through solutions like hybrid power systems and digital energy management, according to the news release.

Goldman Sachs estimates that U.S. data center capacity will more than double from 31 gigawatts in 2025 to 66 gigawatts in 2027. Other reports predict that Houston and Texas will be home to a significant portion of the data center boom, with capacity in the city and the state also expected to double in the next few years.

“The scale and complexity of AI energy infrastructure is fundamentally changing how power systems are built and deployed,” Ron Gusek, CEO of Liberty Energy, added in the release. “Liberty’s comprehensive power service platform is engineered to meet this transition, as customers increasingly prioritize tailored, integrated solutions. Building on our long-standing relationship with SLB, we are excited to bring power solutions that address immediate capacity constraints while supporting the next generation of energy systems.”

SLB sold its onshore hydraulic fracturing business in the United States and Canada to Liberty Energy in December 2020 in exchange for a 37 percent equity interest in the company.

Trending News

A View From HETI

Adam Blake, Nick Poradek and Seth Cohen founded Mavria this spring. Photo courtesy of Mavria

The Woodlands-based Mavria, which mass-produces factory-built modular AI data centers, just emerged from stealth mode with $130 million in funding at a $1 billion valuation.

Mavria raised the money in pre-seed and seed rounds led by Paradigm, an investment firm that concentrates on early-stage startups developing “pioneer” technology. Participants in the funding rounds include AMP PBC, Critical Frontier, Dream Ventures and Liquid 2 Ventures, co-founded by former NFL quarterback Joe Montana.

The company’s inaugural product, Terrain, is a prefabricated data center designed for AI labs, cloud computing providers and data center developers. Mavria says its platform avoids ground-up construction, delivering infrastructure more quickly and at a lower cost.

Mavria tells the Wall Street Journal that the first Terrain unit is being built at a Houston-area factory. The 5-megawatt Terrain system features power distribution, direct liquid cooling, controls and server racks.

“America sets the pace at the intelligence frontier. But the race is moving from the lab into the physical world,” Adam Blake, co-founder and CEO of Mavria, wrote in a blog post.

“Intelligence needs data centers. Data centers need power. Power needs factories, equipment, supply chains, and skilled workers, but much of that infrastructure is still built one custom project at a time, on timelines measured in years.”

Blake and Mavria’s two other co-founders, Nick Poradek and Seth Cohen, most recently worked at the U.S. Department of Energy. There, they focused on reforming the nuclear power sector.

From start to finish, it can take roughly three to six years to build a data center at an estimated cost of $10 million to $37 million per megawatt. Based on those figures, a 100-megawatt data center might cost as much as $3.7 billion.

Here are brief bios of Blake, Poradek and Cohen, who co-founded Mavria in May.

Adam Blake

Blake most recently was a senior advisor to U.S. Energy Secretary Chris Wright. He is co-founder and former CEO of Zego, a provider of energy management technology for property managers. Zego spun out from Brightergy, a commercial solar company. Blake is founder and former CEO of Brightergy.

Nick Poradek

Poradek, chief operating officer at Mavria, was also an advisor to the U.S. energy secretary. He is founder and former CEO of Spring-based Edera Energy, co-founder of The Woodlands-based craft-ice brand Clarity Ice, and founder and former CEO of The Woodlands-based Edera Capital. Poradek sold Edera Energy, a manufacturer of oilfield equipment, to Liberty Energy, a fracking company. Wright is Liberty’s founder and former chairman and CEO.

Seth Cohen

Cohen, chief strategy officer and chief legal officer at Mavria, was head of nuclear law and policy at the Department of Energy. He is also a former NASA advisor and a former attorney at Kirkland & Ellis.

“We believe in rapidly deploying infrastructure as a product, rather than custom-building every project,” Blake said. “We’re bringing together engineering, manufacturing, supply chains and capital so that every project makes us better at delivering the next.”

---

This article originally appeared on our sister site, InnovationMap.

Trending News