making progress

Oxy subsidiary granted landmark EPA permits for carbon capture facility

1PointFive, a subsidiary of Oxy, was granted the first-ever EPA permits for its large-scale carbon capture and sequestration facility in Texas. Photo via 1pointfive.com

Houston’s Occidental Petroleum Corp., or Oxy, and its subsidiary 1PointFive announced that the U.S Environmental Protection Agency approved its Class VI permits to sequester carbon dioxide captured from its STRATOS Direct Air Capture (DAC) facility near Odessa. These are the first such permits issued for a DAC project, according to a news release.

The $1.3 billion STRATOS project, which 1PointFive is developing through a joint venture with investment manager BlackRock, is designed to capture up to 500,000 metric tons of CO2 annually and is expected to begin commercial operations this year. DAC technology pulls CO2 from the air at any location, not just where carbon dioxide is emitted. Major companies, such as Microsoft and AT&T, have secured carbon removal credit agreements through the project.

The permits are issued under the Safe Drinking Water Act's Underground Injection Control program. The captured CO2 will be stored in geologic formations more than a mile underground, meeting the EPA’s review standards.

“This is a significant milestone for the company as we are continuing to develop vital infrastructure that will help the United States achieve energy security,” Vicki Hollub, Oxy president and CEO, said in a news release.“The permits are a catalyst to unlock value from carbon dioxide and advance Direct Air Capture technology as a solution to help organizations address their emissions or produce vital resources and fuels.”

Additionally, Oxy and 1PointFive announced the signing of a 25-year offtake agreement for 2.3 million metric tons of CO2 per year from CF Industries’ upcoming Bluepoint low-carbon ammonia facility in Ascension Parish, Louisiana.

The captured CO2 will be transported to and stored at 1PointFive’s Pelican Sequestration Hub, which is currently under development. Eventually, 1PointFive’s Pelican hub in Louisiana will include infrastructure to safely and economically sequester industrial emissions in underground geologic formations, similar to the STRATOS project.

“CF Industries’ and its partners' confidence in our Pelican Sequestration Hub is a validation of our expertise managing carbon dioxide and how we collaborate with industrial organizations to become their commercial sequestration partner,” Jeff Alvarez, President of 1PointFive Sequestration, said in a news release.

1PointFive is storing up to 20 million tons of CO2 per year, according to the company.

“By working together, we can unlock the potential of American manufacturing and energy production, while advancing industries that deliver high-quality jobs and economic growth,” Alvarez said in a news release.

Trending News

A View From HETI

Fervo's Cape Station project began delivering carbon-free geothermal power in September. Photo courtesy Fervo

Houston-based geothermal power company Fervo Energy has expanded its deal with Longroad Energy for transmission of electricity generated by Fervo’s Utah project.

Fervo added 105 megawatts to its existing 400-megawatt transmission deal with Longroad Energy, a Boston company that develops solar, wind and battery storage projects. The updated agreement will enable Fervo to deliver 505 megawatts of power from its marquee Cape Station geothermal project in Beaver County, Utah.

Dawn Owens, senior vice president of commercial markets at Fervo, said in a release that the new agreement brings another “105 megawatts of long-term, reliable capacity to the grid.”

Subject to regulatory approvals, the new agreement is expected to take effect in 2028.

“Longroad has worked alongside Fervo since its first efforts in Beaver County, and we’re excited to collaborate again,” Charles Spiliotis, chief development officer at Longroad, added in the release. “Providing transmission service for this next phase helps deliver clean, around-the-clock power to the grid.”

Cape Station recently began delivering carbon-free power. Capacity is on track to reach 100 megawatts in early 2027. The project’s second phase is targeted for completion in 2028. It will add 400 megawatts of capacity and is currently under construction.

Cape Station is adjacent to the U.S. Department of Energy’s Frontier Observatory for Research in Geothermal Energy and near the Blundell geothermal power plant.

Earlier this month, Tim Latimer, Fervo’s co-founder, chair, president and CEO, told Wall Street analysts the company had a $11.9 billion backlog of orders in the third quarter, up from $7.2 billion in the previous quarter.

Fervo signed the largest purchase agreement in its history in September with Google. The tech giant agreed to purchase 396 megawatts of geothermal power from Fervo with an option for Google to expand capacity to 1 gigawatt by June 2030. Financial terms weren’t disclosed.