canceled projects

TotalEnergies strikes $1B federal deal to exit offshore wind sector

TotalEnergies is canceling its U.S. offshore wind projects. Photo via totalenergies.com

TotalEnergies, a French company whose U.S. headquarters is in Houston, has agreed to redirect nearly $930 million in capital from two offshore wind leases on the East Coast to oil, natural gas and liquefied natural gas (LNG) production.

In its agreement with the U.S. Department of the Interior, TotalEnergies has also promised not to develop new offshore wind projects in the U.S. “in light of national security concerns,” according to a department press release.

Federal agency hails ‘landmark agreement’

The Department of the Interior called the deal a “landmark agreement” that will steer capital “from expensive, unreliable offshore wind leases toward affordable, reliable natural gas projects that will provide secure energy for hardworking Americans.”

Renewable energy advocates object to what they believe is the Trump administration’s mischaracterization of offshore wind projects.

Under the Department of the Interior agreement, the federal government will reimburse TotalEnergies on a dollar-for-dollar basis for the leases, up to the amount that the energy company paid.

“Offshore wind is one of the most expensive, unreliable, environmentally disruptive, and subsidy-dependent schemes ever forced on American ratepayers and taxpayers,” Interior Secretary Doug Burgum said in the announcement. “We welcome TotalEnergies’ commitment to developing projects that produce dependable, affordable power to lower Americans' monthly bills while providing secure U.S. baseload power today — and in the future.”

TotalEnergies cites U.S. policy in move away from U.S. wind power

In the news release, Patrick Pouyanné, chairman and CEO of TotalEnergies, says the company was “pleased” to sign the agreement to support the Trump administration’s energy policy.

“Considering that the development of offshore wind projects is not in the country’s interest, we have decided to renounce offshore wind development in the United States, in exchange for the reimbursement of the lease fees,” Pouyanné says.

TotalEnergies redirects capital to LNG, oil, and natural gas

TotalEnergies will use the $928 million it spent on the offshore wind leases for development of a joint venture LNG plant in the Rio Grande Valley, as well as for production of upstream oil in the Gulf of Mexico and for production of shale gas.

“These investments will contribute to supplying Europe with much-needed LNG from the U.S. and provide gas for U.S. data center development. We believe this is a more efficient use of capital in the United States,” Pouyanné says.

TotalEnergies paid $133.3 million for an offshore wind lease at the Carolina Long Bay project off the coast of North Carolina and $795 million in 2022 for a lease covering a 1,545-megawatt commercial offshore wind facility off the coast of New Jersey.

“TotalEnergies’ studies on these leases have shown that offshore wind developments in the United States, unlike those in Europe, are costly and might have a negative impact on power affordability for U.S. consumers,” TotalEnergies said in a company-issued press release. “Since other technologies are available to meet the growing demand for electricity in the United States in a more affordable way, TotalEnergies considers there is no need to allocate capital to this technology in the U.S.”

Since 2022, TotalEnergies has invested nearly $12 billion to promote the development of oil, LNG, and electricity in the U.S. In 2025, TotalEnergies was the No. 1 exporter of LNG from the U.S.

Industry groups push back on offshore wind pullback

The American Clean Energy Association has pushed back on the Trump administration’s characterization of offshore wind projects.

“The offshore wind industry creates thousands of high-quality, good-paying jobs, and is revitalizing American manufacturing supply chains and U.S. shipyards,” Jason Grumet, the association’s CEO, said in December after the Trump administration paused all leases for large-scale offshore wind projects under construction in the U.S. “It is a critical component of our energy security and provides stable, domestic power that helps meet demand and keep costs low.”

Grumet added that President Trump’s “relentless attacks on offshore wind undermine his own economic agenda and needlessly harm American workers and consumers.” He called for passage of federal legislation that would prevent the White House “from picking winners and losers” in the energy sector and “placing political ideology” above Americans’ best interests.

The National Resources Defense Council offered a similar response to the offshore wind leases being paused.

“In its ongoing effort to prop up waning fossil fuels interests, the administration is taking wilder and wilder swings at the clean energy projects this economy needs,” said Pasha Feinberg, the council’s offshore wind strategist. “Investments in energy infrastructure require business certainty. This is the opposite. If the administration thinks the chilling impacts of this action are limited to the clean energy sector, it is sorely mistaken.”

Trending News

A View From HETI

Scotty Nyquist discuss the growth in AI data centers and the strain on the system. Photo via HARC report

For most of the past 20 years, U.S. electricity policy relied on predictable trends in demand. Electricity use, in most regions, increased gradually, forecasts were stable, and utilities adjusted the system in small steps. Power plants, transmission lines, and substations were generally added to reflect shifts in load, rather than growth, and costs were recovered through modest adjustments to customer bills.

Growth in AI data centers has disrupted this model. A single facility can add as much electricity demand as a small town. That demand comes all at once, runs continuously, and has little tolerance for outages. If electricity service drops even briefly, computation stops, and services shut down. Ironically, data centers need reliable service, a point that their emergence is driving concern around for the rest of the grid.

What the numbers say

The International Energy Agency projects global electricity consumption from data centers to double by 2030, reaching roughly 945 TWh, nearly 3 percent of global electricity demand, with consumption growing about 15 percent per year this decade. McKinsey projects that U.S. data center demand alone could grow 20–25 percent per year, with global capacity demand more than tripling by 2030.

After years of roughly 0.5 percent annual demand growth, many forecasts now place total U.S. electricity demand growth closer to 2–3 percent per year through the mid-2030s, with much higher growth in specific regions. In Texas, some forecasters are saying electricity demand could double over the next five years, a staggering 10 percent per year growth rate. What sounds incremental on paper translates into a major challenge on the ground. Meeting this pace of growth is estimated to require $250–$300 billion per year in grid investment, about double what the system has been absorbing.

Where the system starts to strain

The strain appears first in the interconnection queue. It shows up as long waits, backlogs, and delays for connecting new loads and new generation.

Before new generators or large load customers can be connected, a study is required to assess their impact on the grid, whether it can physically handle the added load, and whether upgrades are required. With AI-driven data centers, utilities face far more connection requests than they can realistically support. In ERCOT, large-load interconnection requests exceed 200 gigawatts, most tied to data centers. That amount exceeds historical norms, and it is several times larger than what can be practically studied or built in the near term.

To be clear, public utility commissions are required to study these requests because they must manage system capabilities to ensure minimal disruption. This means engineers spend time evaluating projects that may never be built, while other more commercially viable projects may wait longer for approvals. This extends timelines and makes infrastructure planning less reliable.

Why policymakers are rethinking the rules

Utilities and their regulators must decide how much generation, transmission, and substation capacity to build years before it comes online. Those decisions are based on expected demand at the time projects are approved. When it comes to data centers, by the time infrastructure is completed, they may end up deploying newer, more efficient chips that use less power than originally assumed. This can result in grid infrastructure built for a higher load than what actually materializes, leaving excess capacity that still must be paid for through system-wide rates.

That’s the central dilemma. If utilities build too little capacity, the system operates with less reserve margin. During periods of grid stress, operators have fewer options, increasing the likelihood of curtailments or outages. However, if utilities build too much, customers may be asked to pay for infrastructure that is not fully used.

In response, policymakers are adjusting the rules. In some regions, regulators are moving toward bring-your-own-power approaches that require large data centers to supply or fund part of the capacity needed to serve them or reduce demand during system stress. At the federal level, permitting reforms tied to datacenter infrastructure increasingly treat electricity as a strategic economic input.

As Ken Medlock, senior director at the Baker Institute Center for Energy Studies (CES), explains:

“Many of the planned data centers are now also adding behind-the-meter options to their development plans because they do not anticipate being able to manage their needs solely from the grid, and they certainly cannot do so with only intermittent power sources.”

Behind-the-meter (BTM) refers to power that a consumer controls on its side of the utility meter, such as on-site gas generation or a dedicated power plant. These resources allow data centers to keep operating during grid-related service. Most facilities remain connected to the grid, but the backup BTM generation serves as insurance for operating their core business.

This shifts responsibility. Utilities traditionally manage reliability across all customers by maintaining an operating reserve margin, or spare capacity. Increasingly, large-load customers manage part of their own electricity reliability needs, which changes how infrastructure is planned and how risk is distributed.

Bottom line

AI-driven load growth is arriving faster and in more concentrated places than the power system was built to accommodate. Utilities and regulators are being forced to make decisions sooner than planned about where to build, how fast to build, and which customers get priority when capacity is limited. The effects extend beyond data centers, showing up in system costs, reliability margins, competition for grid access, and pressure on communities and industries that depend on affordable and dependable power. The issue is not whether electricity can be generated, but how the costs and risks of rapid demand growth are distributed as the system tries to keep up. How regulators balance these decisions will determine who pays as AI demand outruns the power grid.

-----------

Scott Nyquist is a senior advisor at McKinsey & Company and vice chairman, Houston Energy Transition Initiative of the Greater Houston Partnership. The views expressed herein are Nyquist's own and not those of McKinsey & Company or of the Greater Houston Partnership. This article originally appeared on LinkedIn.