San Antonio company breaks ground on 347MW solar project outside of Houston

SunRoper Solar is slated to begin operations in December 2027. Photo courtesy OCI Energy

Crews have broken ground on the forthcoming 347-megawatt direct-current SunRoper Solar project in Wharton County, Texas, that will add capacity to the ERCOT grid.

The solar project, which is slated to begin operations in December 2027, will provide electricity to an undisclosed Fortune 100 company under a long-term power purchase agreement, according to a news release.

San Antonio’s OCI Energy and Israel's Arava Power are developing the project. It's being financed by ING Capital and constructed by Louisiana-based WHC Inc. The project received $394 million in construction financing in February.

"SunRoper demonstrates how strategic partnerships can help meet Texas' growing demand for electricity through investments in critical energy infrastructure," Sabah Bayatli, president of OCI Energy, said in the release.

Project partners, landowners and company executives attended a groundbreaking event for SunRoper on Sept. 1 at the site outside of the Houston metro area. The companies say they are advancing this energy project to strengthen grid reliability and to help deliver affordable power to one of the highest-demand areas in the state.

“WHC is proud to serve as EPC contractor on the SunRoper Solar project, bringing our construction expertise to bear on a facility that will deliver meaningful power to the Houston region,” Randel Badeaux, president of power North America for WHC, added in the news release. “This groundbreaking reflects months of careful planning and coordination with OCI Energy, Arava Power and our project partners, and we look forward to executing a safe, high-quality build through to completion in 2027.”

OCI Energy currently operates several utility-scale solar and battery energy storage system projects outside of the San Antonio area, and has five other projects under construction outside of San Antonio and Waco, with more than 30 under development in Arkansas, Mississippi, Georgia, Colorado and Alberta, Canada. The company also has existing projects in New Jersey and Georgia.

Trending News

A View From HETI

Meta's data center in Temple, Texas. Rendering courtesy Meta

Responding to public outcry, Gov. Greg Abbott has stepped up his campaign against data centers by temporarily halting approval of environmental permits for data center projects.

This and previous moves by Abbott essentially amount to a temporary freeze on the development of new data centers in Texas. His actions come at a time when Texas’ stature as a data center hub has been soaring.

On Monday, Abbott directed the Texas Commission on Environmental Quality to stop issuing permits for data center developments until the Electric Reliability Council of Texas (ERCOT) and Public Utility Commission of Texas complete their review of projects seeking power grid connections.

With regulatory reviews underway and environmental permitting now frozen, state regulators currently cannot approve or deny requests from data center developers, Abbott said.

In a letter to the environmental quality commission’s executive director, Kelly Keel, Abbott said this directive is “consistent with my whole-of-government approach to ensure Texans’ natural resources and way of life are protected.”

Abbott previously ordered the Texas Water Development Board to require data centers to meet reporting requirements for water use. He also told the board to impose penalties for failure to comply with those requirements and to collaborate with ERCOT on its review.

Abbott launched his crackdown on data centers in August by ordering the Public Utility Commission and ERCOT to review data center projects in Texas. The audits will examine all data centers in the queue for interconnections before any more projects can move forward. Interconnections enable data centers to share power, data and computing resources.

In calling for those audits, Abbott cited concerns over data centers’ use of water and electricity, and the centers’ effect on infrastructure expenses and consumers’ utility rates.

“Simply put, Texans must come first,” the governor said.

During next year’s legislation session, Abbott will push for the elimination of state financial incentives for data center projects.

Ed Hirs, an energy fellow ⁠at the University of Houston, told Reuters that Abbott was backtracking on “his earlier pronouncements about data centers leading to lower electricity prices.”

Abbott’s actions come amid growing public backlash over data centers. A recent University of Houston survey found that nearly 63 percent of Houston-area residents opposed construction of a data center within a mile of their home.