solar funding

Houston-area solar farm to move forward with $394M in construction financing

San Antonio-based OCI Energy is developing Project SunRope outside of Houston. Photo via Pexels.com

Project SunRope, a 347-megawatt solar project outside of Houston, has landed $394 million in construction financing.

The project, located in Wharton County, about 60 miles outside of Houston, is slated to begin commercial operation in Q3 2027 and aims to support emission reductions, grid reliability and affordability in one of the highest electricity-demand regions in Texas and the U.S. It’s being developed through a joint venture between San Antonio-based OCI Energy and leading Israeli solar company Arava Power. New York-based ING Capital underwrote the financing package.

“The close of construction financing for Project SunRoper represents an important milestone for OCI Energy and our partners,” Sabah Bayatli, resident of OCI Energy, said in a news release. “This transaction reflects our continued commitment to deliver high-quality, utility-scale solar projects that strengthen grid reliability and provide affordable energy infrastructure.”

The construction financing is supported by a 20-year power purchase agreement with a Fortune 100 company, according to the release. Other collaborators include BHI and Bank of Hapoalim, which provided financing support and letters of credit to support the development of the project.

This is the second transaction between OCI Energy and ING, as they previously worked together on financing for the Alamo City Battery Energy Storage System, a 120-megawatt battery energy storage system under development in Bexar County.

“This project exemplifies the high‑quality renewable infrastructure we seek to finance – a strong sponsor partnership, a long‑term contracted revenue profile, and a well‑located asset in one of the most dynamic power markets in the United States,” Sven Wellock, managing director at ING, added in the release. “We are proud to build on our existing relationship with OCI Energy and to partner with Arava Power on its continued expansion in the U.S. market, advancing a project that will deliver reliable, affordable clean energy for years to come.”

OCI Energy operates several utility-scale solar and battery energy storage system projects outside of the San Antonio area, as well as in Georgia and New Jersey. It has five other projects under construction outside of San Antonio and Waco, with more than 20 under development throughout the state.

Trending News

A View From HETI

Meta's data center in Temple, Texas. Rendering courtesy Meta

Responding to public outcry, Gov. Greg Abbott has stepped up his campaign against data centers by temporarily halting approval of environmental permits for data center projects.

This and previous moves by Abbott essentially amount to a temporary freeze on the development of new data centers in Texas. His actions come at a time when Texas’ stature as a data center hub has been soaring.

On Monday, Abbott directed the Texas Commission on Environmental Quality to stop issuing permits for data center developments until the Electric Reliability Council of Texas (ERCOT) and Public Utility Commission of Texas complete their review of projects seeking power grid connections.

With regulatory reviews underway and environmental permitting now frozen, state regulators currently cannot approve or deny requests from data center developers, Abbott said.

In a letter to the environmental quality commission’s executive director, Kelly Keel, Abbott said this directive is “consistent with my whole-of-government approach to ensure Texans’ natural resources and way of life are protected.”

Abbott previously ordered the Texas Water Development Board to require data centers to meet reporting requirements for water use. He also told the board to impose penalties for failure to comply with those requirements and to collaborate with ERCOT on its review.

Abbott launched his crackdown on data centers in August by ordering the Public Utility Commission and ERCOT to review data center projects in Texas. The audits will examine all data centers in the queue for interconnections before any more projects can move forward. Interconnections enable data centers to share power, data and computing resources.

In calling for those audits, Abbott cited concerns over data centers’ use of water and electricity, and the centers’ effect on infrastructure expenses and consumers’ utility rates.

“Simply put, Texans must come first,” the governor said.

During next year’s legislation session, Abbott will push for the elimination of state financial incentives for data center projects.

Ed Hirs, an energy fellow ⁠at the University of Houston, told Reuters that Abbott was backtracking on “his earlier pronouncements about data centers leading to lower electricity prices.”

Abbott’s actions come amid growing public backlash over data centers. A recent University of Houston survey found that nearly 63 percent of Houston-area residents opposed construction of a data center within a mile of their home.