California company launches Tesla Megapack battery project in Houston area

Nightpeak Energy's Bocanova Power project in Brazoria County has reached commercial operation. Photo courtesy Nightpeak Energy.

Oakland, California-based Nightpeak Energy announced earlier this month that its 150-megawatt battery storage project in Brazoria County, known as Bocanova Power, is now operating to address Houston’s peak capacity needs.

“This battery storage project will enhance grid reliability in the Alvin area while continuing to support integrating renewable energy,” Cary Perrin, president and CEO of the Northern Brazoria County Chamber of Commerce, said in a news release. “I believe we need energy storage now more than ever for its pivotal role in reducing strain on the grid while meeting fast-growing power demand in Texas and Brazoria County."

The project reached commercial operation in August, according to the release. The project utilizes Tesla's Megapack 2 XL battery storage system, and the facility operates under a long-term power purchase agreement with an undisclosed “investment-grade power purchaser.”

“Bocanova Power demonstrates the speed at which Nightpeak Energy is overcoming complex challenges to energize projects that support America's growing need for affordable, reliable, and secure energy,” Paris Hays, co-founder and CEO/CDO of Nightpeak Energy, added in the news release. “Unprecedented AI data center and manufacturing growth has only accelerated the need for these resources.”

Hays added in the release that the company has plans for more energy infrastructure projects in Texas and in the Western U.S.

Nightpeak Energy develops, owns and operates power plants that support the growing capacity needs of a decarbonized grid. It also owns and operates 240 MW of battery storage and natural gas generation facilities.

The company was founded in 2022 and backed by equity funding of up to $200 million from Dallas-based investment firm Energy Spectrum Capital.

Trending News

A View From HETI

Fervo Energy has released its third-quarter earnings. Photo via fervoenergy.com

Houston-based geothermal power company Fervo Energy saw a 65 percent spike in purchase orders during the third quarter.

During Fervo’s third-quarter earnings call, Tim Latimer, co-founder, chair, president and CEO, said the company had a $11.9 billion backlog of orders, up from $7.2 billion in the previous quarter.

Those numbers didn’t translate to robust financial results in the third quarter, though. It closed the quarter with an operating loss of $43 million on revenue of just $116,000.

Beyond the billions of dollars in signed purchase agreements, Fervo is in talks with prospective customers in the utility, industrial data-center sectors, Latimer said. About half the potential customers are in the data-center sector, 35 percent in the utility sector and 15 percent in the industrial sector.

Latimer said the broad-based demand reflected by the backlog and the discussions with potential customers reinforces the critical need for reliable, readily available power.

“Our approach to power delivery will continue to blend front-of-the-meter and behind-the-meter development,” he said. “Grid-connected assets remain the foundation, though behind-the-meter gives customers a faster path to power when transmission time lines lag their need.”

Front-of-the-meter refers to power plants, utility-scale solar and wind farms, large grid batteries, and transmission and distribution infrastructure. Behind-the-meter assets sit on the customer side of the meter, such as backup generators and EV chargers at homes, businesses, factories and other everyday places.

The order backlog isn’t Fervo’s only recent milestone. In late September, the company’s Cape Station geothermal plant in Utah started delivering its first utility-scale geothermal power to the grid. The plant is producing about 33 megawatts of power.

Earlier in September, Fervo signed a 15-year deal to supply about 396 megawatts of power for Google data centers. The power will be delivered in four 99-megawatt batches. The company filed its $1.89 billion IPO this spring.