Meta's data center in Temple, Texas. Rendering courtesy Meta

Responding to public outcry, Gov. Greg Abbott has stepped up his campaign against data centers by temporarily halting approval of environmental permits for data center projects.

This and previous moves by Abbott essentially amount to a temporary freeze on the development of new data centers in Texas. His actions come at a time when Texas’ stature as a data center hub has been soaring.

On Monday, Abbott directed the Texas Commission on Environmental Quality to stop issuing permits for data center developments until the Electric Reliability Council of Texas (ERCOT) and Public Utility Commission of Texas complete their review of projects seeking power grid connections.

With regulatory reviews underway and environmental permitting now frozen, state regulators currently cannot approve or deny requests from data center developers, Abbott said.

In a letter to the environmental quality commission’s executive director, Kelly Keel, Abbott said this directive is “consistent with my whole-of-government approach to ensure Texans’ natural resources and way of life are protected.”

Abbott previously ordered the Texas Water Development Board to require data centers to meet reporting requirements for water use. He also told the board to impose penalties for failure to comply with those requirements and to collaborate with ERCOT on its review.

Abbott launched his crackdown on data centers in August by ordering the Public Utility Commission and ERCOT to review data center projects in Texas. The audits will examine all data centers in the queue for interconnections before any more projects can move forward. Interconnections enable data centers to share power, data and computing resources.

In calling for those audits, Abbott cited concerns over data centers’ use of water and electricity, and the centers’ effect on infrastructure expenses and consumers’ utility rates.

“Simply put, Texans must come first,” the governor said.

During next year’s legislation session, Abbott will push for the elimination of state financial incentives for data center projects.

Ed Hirs, an energy fellow ⁠at the University of Houston, told Reuters that Abbott was backtracking on “his earlier pronouncements about data centers leading to lower electricity prices.”

Abbott’s actions come amid growing public backlash over data centers. A recent University of Houston survey found that nearly 63 percent of Houston-area residents opposed construction of a data center within a mile of their home.

D.C.-based Last Energy plans to bring 30 micro-nuclear reactors in Texas online within the next two years. Rending courtesy Last Energy.

Energy co. to build 30 micro-nuclear reactors in Texas to meet rising demand

going nuclear

A Washington, D.C.-based developer of micro-nuclear technology plans to build 30 micro-nuclear reactors near Abilene to address the rising demand for electricity to operate data centers across Texas.

The company, Last Energy, is seeking permission from the Electric Reliability Council of Texas (ERCOT) and the U.S. Nuclear Regulatory Commission to build the microreactors on a more than 200-acre site in Haskell County, about 60 miles north of Abilene.

The privately financed microreactors are expected to go online within roughly two years. They would be connected to ERCOT’s power grid, which serves the bulk of Texas.

“Texas is America’s undisputed energy leader, but skyrocketing population growth and data center development is forcing policymakers, customers, and energy providers to embrace new technologies,” says Bret Kugelmass, founder and CEO of Last Energy.

“Nuclear power is the most effective way to meet Texas’ demand, but our solution—plug-and-play microreactors, designed for scalability and siting flexibility—is the best way to meet it quickly,” Kugelmass adds. “Texas is a state that recognizes energy is a precondition for prosperity, and Last Energy is excited to contribute to that mission.”

Texas is home to more than 340 data centers, according to Perceptive Power Infrastructure. These centers consume nearly 8 gigawatts of power and make up 9 percent of the state’s power demand.

Data centers are one of the most energy-intensive building types, says to the U.S. Department of Energy, and account for approximately 2 percent of the total U.S. electricity use.

Microreactors are 100 to 1,000 times smaller than conventional nuclear reactors, according to the Idaho National Laboratory. Yet each Last Energy microreactor can produce 20 megawatts of thermal energy.

Before announcing the 30 proposed microreactors to be located near Abilene, Last Energy built two full-scale prototypes in Texas in tandem with manufacturing partners. The company has also held demonstration events in Texas, including at CERAWeek 2024 in Houston. Last Energy, founded in 2019, is a founding member of the Texas Nuclear Alliance.

“Texas is the energy capital of America, and we are working to be No. 1 in advanced nuclear power,” Governor Greg Abbott said in a statement. “Last Energy’s microreactor project in Haskell County will help fulfill the state’s growing data center demand. Texas must become a national leader in advanced nuclear energy. By working together with industry leaders like Last Energy, we will usher in a nuclear power renaissance in the United States.”

Nuclear energy is not a major source of power in Texas. In 2023, the state’s two nuclear power plants generated about 7% of the state’s electricity, according to the U.S. Energy Information Administration. Texas gains most of its electricity from natural gas, coal, wind, and solar.

FluxWorks, a hardtech startup, opened its new home-base in Conroe, Texas. Photo courtesy FluxWorks

Hardtech startup moves HQ to Houston area with new Conroe facility

moving in

FluxWorks, a hardtech startup, recently opened its new base of operations in Workhub Developments’ Conroe location.

Founded in College Station by CEO Bryton Praslicka, FluxWorks specializes in making contactless magnetic gears for use in extreme conditions. At 9,000 square feet, the new Conroe facility is a result of discussions with Governor Greg Abbott's office and the Greater Houston Partnership, who introduced the company’s leadership to the Conroe Economic Development Council, encouraging their move, Praslicka tells InnovationMap.

“The pieces of the puzzle were all there, and with the support of the local, state, and federal government, we were thrilled to move to Conroe,” Paslicka says.

The enterprise recently won the MassChallenge’s technology in space prize, allowing them to test four gears at the International Space Station (ISS) National Laboratory in 2026. The prize is funded by Boeing and the Center for the Advancement of Science in Space, or CASIS which runs the ISS. Praslicka says their new offices will expand their manufacturing capacity by having all levels of production on-site.

FluxWorks has moved into its 9,000-square-foot facility in Conroe. Photo courtesy FluxWorks

"Since our inception, FluxWorks has been fragmented, having an office in one location, manufacturing in another location, and testing in a third location," Praslicka explains. "This is a new chapter for us to begin having the entire process, from design to testing and validation and then shipping to customers, all under one house.”

The magnetic gears FluxWorks makes are suited to space applications because they do not require lubricants, which can be difficult to control at harsh temperatures and in microgravity, to minimize friction. Through their partnership with the ISS, Praslicka says FluxWorks has strengthened their connections to other space tech companies including Axiom and Boeing, and it's opened the door to collaborations with the new Texas Space Commission.

“Now the NASA Johnson Space Center is even officially supporting our proposal to the Texas Space Commission as a proposed teaming partner,” Praslicka says.

The new facility received special security certification from the National Institute of Standards and Technology, increasing FluxWorks’ opportunities to work with NASA and defense contractors. The Texas Manufacturing Assistance Center awarded FluxWorks for “outstanding innovation” during its recent ribbon cutting ceremony.

The company, named a finalist for the 2024 Houston Innovation Awards, cleaned up in the 2023 Rice Business Plan Competition with a $350,000 investment prize from Houston group, Goose Capital.

———

This article originally ran on InnovationMap.

Governor Abbott said he was sending a letter to the Public Utility Commission of Texas requiring it to investigate why restoration has taken so long and what must be done to fix it. Photo via X/Governor Abbott

Texas Gov. Greg Abbott demands answers from Houston power company following Beryl

investigation incoming

With around 270,000 homes and businesses still without power in the Houston area almost a week after Hurricane Beryl hit Texas, Gov. Greg Abbott on Sunday said he's demanding an investigation into the response of the utility that serves the area as well as answers about its preparations for upcoming storms.

“Power companies along the Gulf Coast must be prepared to deal with hurricanes, to state the obvious,” Abbott said at his first news conference about Beryl since returning to the state from an economic development trip to Asia.

While CenterPoint Energy has restored power to about 2 million customers since the storm hit on July 8, the slow pace of recovery has put the utility, which provides electricity to the nation’s fourth-largest city, under mounting scrutiny over whether it was sufficiently prepared for the storm that left people without air conditioning in the searing summer heat.

Abbott said he was sending a letter to the Public Utility Commission of Texas requiring it to investigate why restoration has taken so long and what must be done to fix it. In the Houston area, Beryl toppled transmission lines, uprooted trees and snapped branches that crashed into power lines.

With months of hurricane season left, Abbott said he's giving CenterPoint until the end of the month to specify what it'll be doing to reduce or eliminate power outages in the event of another storm. He said that will include the company providing detailed plans to remove vegetation that still threatens power lines.

Abbott also said that CenterPoint didn't have “an adequate number of workers pre-staged" before the storm hit.

Following Abbott's news conference, CenterPoint said its top priority was “power to the remaining impacted customers as safely and quickly as possible,” adding that on Monday, the utility expects to have restored power to 90% of its customers. CenterPoint said it was committed to working with state and local leaders and to doing a “thorough review of our response.”

CenterPoint also said Sunday that it’s been “investing for years” to strengthen the area’s resilience to such storms.

The utility has defended its preparation for the storm and said that it has brought in about 12,000 additional workers from outside Houston. It has said it would have been unsafe to preposition those workers inside the predicted storm impact area before Beryl made landfall.

Brad Tutunjian, vice president for regulatory policy for CenterPoint Energy, said last week that the extensive damage to trees and power poles hampered the ability to restore power quickly.

A post Sunday on CenterPoint's website from its president and CEO, Jason Wells, said that over 2,100 utility poles were damaged during the storm and over 18,600 trees had to be removed from power lines, which impacted over 75% of the utility's distribution circuits.

It will take days to recover from Hurricane Beryl. Photo by Brandon Bell/Getty Images

Houston residents face high temperatures after storm Beryl leaves millions without power

lights out

The return of searing heat in the Houston area has deepened the misery for people still without power after Hurricane Beryl left residents in search of places to cool off and fuel up as the extended outages strained one of the nation’s largest cities.

More than 1.7 million homes and businesses in Texas lacked electricity Wednesday morning, down from a peak of over 2.7 million on Monday, according to PowerOutage.us. State officials faced questions over whether the power utility that covers much of the area had sufficiently prepared.

Texas Lt. Gov. Dan Patrick said that a sports and event complex would be used to temporarily hold up to 250 hospital patients who are awaiting discharge but cannot be released to homes with no power.

Beryl, which made landfall in Texas early Monday as a Category 1 hurricane, has been blamed for at least seven U.S. deaths — one in Louisiana and six in Texas — and at least 11 in the Caribbean. It weakened as it moved deeper into the U.S. and early Wednesday was a post-tropical cyclone centered over northeastern Indiana.

A flood watch was in effect for parts of Illinois, Indiana, Michigan, New York, Vermont, New Hampshire and Maine. The storm spawned suspected tornadoes in parts of Indiana and Kentucky.

In the Houston area, Beryl compounded and repeated the misery of May, when storms killed eight people and left nearly 1 million without power.

High temperatures Tuesday climbed into the 90s (above 32.2 Celsius) with humidity that made it feel even hotter. Similar heat and humidity were expected Wednesday. The National Weather Service described the conditions as potentially dangerous, given the lack of power and air conditioning.

People coped as best they could. Kyuta Allen took her family to a Houston community center to cool down and use the internet.

“During the day you can have the doors open, but at night you’ve got to board up and lock up — lock yourself like into a sauna,” she said.

An executive for CenterPoint Energy, which covers much of the Houston area, defended the utility’s preparation and response.

“From my perspective, to have a storm pass at 3 p.m. in the afternoon, have those crews come in in the late evening, and have everything ready by 5 a.m. to go out and get out and start the workforce is rather impressive, because we’re talking about thousands of crews,” said Brad Tutunjian, vice president of regulatory policy.

Nim Kidd, head of the state’s division of emergency management, stressed that restoring power was the top priority.

Patrick, who is acting as governor while Gov. Greg Abbott is overseas, said nursing homes and assisted living centers were the highest priority. Sixteen hospitals ran on generator power Tuesday morning, according to the Federal Emergency Management Agency.

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Fervo produces first geothermal power at flagship Utah project

energy milestone

Fervo Energy’s flagship project in Utah just generated its first geothermal power.

The electricity is now flowing to the power grid from one of Cape Station’s three generation units, Houston-based Fervo said in a news release. This represents an early but important milestone for the project, as the unit isn’t scheduled to deliver contracted power until Oct. 1.

The achievement, coming four months after Fervo’s roughly $2.2 billion IPO, demonstrates the viability of enhanced geothermal systems (EGS).

“This is a gamechanger for the geothermal industry. It establishes EGS as the defining new power generation technology of our time, and we believe it shows that the commercial and technical maturity of EGS is ready to meet the urgent need for reliable, clean power,” Tim Latimer, co-founder and CEO of Fervo, said in the release.

The plant’s two other units are scheduled to launch commercial operations on Jan. 1.

The three units make up the project’s 99-megawatt first phase. The next phase, which will add 400 megawatts of capacity, is under construction. The second phase is set to go online in 2028.

Altogether, Cape Station will provide more than 4 gigawatts of capacity, with 900 megawatts already spoken for. The 900 megawatts of contracted electricity would be enough to power nearly 1 million U.S. homes per year.

“Cape Station works because we treated the subsurface like an engineering challenge,” Jack Norbeck, co-founder and chief technology officer of Fervo, added in the release. “Years of drilling, completion design, subsurface modeling, and flow testing led to this moment, and this is the validation that matters most.”

Enhanced geothermal continuously draws on heat that’s deep underground, producing electricity around the clock regardless of weather or time of day. That makes it one of the only carbon-free resources capable of constant power delivery, which is critical for data centers and AI infrastructure.

Expert: Houston Energy and Climate Week showcases a city building the future

guest column

While hundreds of thousands descend on New York for Climate Week, Houston offered a different proposition: come where the work is being built. And last week Houston proved that it’s solving for more energy and fewer emissions; reliability and affordability; speed and durability. We are solving for the “&.”

That equation sharpened last week. On Sept. 14, the Environmental Protection Agency announced it had repealed most 2024 federal carbon-pollution standards for power plants and proposed rescinding remaining greenhouse-gas requirements. Policy matters, but it can pivot. The need to build does not.

HECW is a proving ground, not another conference stop. As I wrote in the Houston Chronicle, Mayor Sylvester Turner planted the seed by insisting we bring people together across the city and industry to drive Houston’s energy future. He knew false choices have no place here: oil and gas and clean technology; prosperity and stewardship; industry and lower emissions.

ECW joined the Climate Week Network this year, connecting Houston to a growing community of more than 500,000 people across 22-plus cities. We now have a seat at the global table—and a responsibility to use it well, building with other cities and the wider clean-energy-solutions world rather than merely talking at them.

The capital is already moving. Since 2017, Houston Energy Transition Initiative member companies have invested more than $95 billion in low-carbon infrastructure, technologies, and research and development. This is where the transition is financed, engineered, tested and operated. But the work requires more than capital. It requires capital allocators who understand the difference between a promising idea and a project that can scale, hire and endure.

Last week was Houston’s show and tell. At ARTECHOUSE, The &Bassador Reception & Awards brought art, technology, culture, philanthropy and energy together. Then the week went beyond downtown.

Sugar Land Town Square became the launchpad for the Metro Innovation Tour & Market: a place for an ecosystem conversation about smart cities, clean energy, equitable access and next-generation mobility before participants boarded three tour routes across greater Houston. It was also the starting point for the Bay City South Innovation Tour to Erthos Project Bravo in Matagorda County, where small groups saw Earth Mount solar modules being installed in real time. The conversation did not end at a panel. It went to the project site.

The HTX Tech Tours included a visit to the Erthos Project Bravo in Matagorda County. Photo courtesy

Approximately 100 startups from around the world pitched at Rice Alliance, Greentown Labs and Halliburton Labs events. At Astros Night at Daikin Park, builders, backers, and believers traded conference rooms for the diamond, creating an experience, not just another event. That is how this work becomes civic fabric.

Activation also means making the energy story felt, not merely explained. AY Young brought the Battery Tour for live performances. It was a reminder that the “Power of &” is not confined to a boardroom or a laboratory. Art and technology, culture and commerce, a new generation and established industry can share the same stage—and help more people see themselves in the work ahead.

Perhaps no activation made the “Power of &” more immediate and real than the Houston, We Have Solutions open mic night. At Creatopia’s Innovation Studio, people took the mic—or simply listened—to share what they were building, the problem they could not stop thinking about, and the connection they hoped to make. It put founders, artists, community builders, researchers and future-makers in one room. That is collaboration in real time: different kinds of expertise meeting before anyone knows exactly what the solution will be.

FOX26 helped carry that story beyond the rooms we convened, hosting Erthos COO Jessica Knight, Mars Materials co-founder Aaron Fitzgerald, and investors Taylor Chapman and Juliana Garaizar to discuss building and backing the future in Houston. Our region should be proud—not as self-congratulation, but because the world is beginning to experience energy and climate solutions firsthand.

This was also a week to give back. Allies in Energy awarded $27,500 to nine organizations advancing energy and climate literacy, civil dialogue, workforce pathways and community action. NRG Energy’s Brighter Communities provided a founding gift to expand the week and fund local grants. It took partners, hosts, sponsors, volunteers, funders and community organizations. That is the “Power of &”: collaboration that leaves a stronger community behind.

The “Power of &” cannot stop at Houston’s city limits. Louisiana’s participation—through its support of the Digital Delta Symposium & Expo—made clear that Houston’s builder ecosystem is regional by necessity. Gulf Coast infrastructure, supply chains, talent, and industrial decisions do not recognize state lines. Neither should our collaboration. If we are serious about building more energy with fewer emissions, we must align capital, resources and opportunity across the entire Gulf Coast.

That same commitment to practical collaboration means listening, learning and adjusting. A builder’s mindset does not protect a plan simply because it came first; it improves the conditions for the work to succeed. That is why Houston Energy and Climate Week will move to April 4–10, 2027—better weather, more time and space for connection, and a stronger city-wide experience for the people building what comes next.

But the real test begins now. Can we keep widening the circle? Can we continue to turn research into projects, pilots into infrastructure, capital into good jobs and climate ambition into results that families and communities can see? Can we make every new solution stronger by bringing in the people who must finance it, build it, operate it, live beside it and benefit from it?

That is the work ahead. Turner understood that Houston does not move forward by asking who wins the argument. It moves forward by asking who is ready to solve the problem. His legacy—and the promise of the “&”—is an invitation to choose collaboration over division, action over performance and possibility over false choices.

The future does not need another city to talk about it. It needs Houston to keep building it. And it will only be built if we keep choosing the "&."

---

Katie Mehnert is the CEO of The Bee Suite, and a recent partner to The Builder’s Movement.

Only 8 of 160 utility companies in Texas have filed wildfire response plans

Utility News

Only eight of 160 utility companies that operate in fire-prone areas of Texas have complied with a law that helps mitigate wildfires, lawmakers recently learned. The revelation comes on the heels of a chaotic wildfire season that has continued through the summer.

Lawmakers learned about the slow progress last week during a House State Affairs committee hearing, led by Rep. Ken King, who led the charge on the new law last year. The law under House Bill 145 requires utility companies to file wildfire mitigation plans to the Public Utility Commission.

The plans must include emergency protocols in the case of a wildfire, utility operating plans during high-risk weather conditions, management of grass, shrubs and other vegetation in areas that are at risk of wildfires, inspection of poles and other electric equipment and identified areas of wildfire risks within a utility’s service territory.

King, a Republican from Canadian where much of the wildfire damage occurred during the Panhandle wildfires, pressed utility companies on the lack of compliance.

“I’m very, very disappointed with the industry,” King said. “I think it’s imperative for anybody that has not filed that report to realize January is coming. You will file that wildfire mitigation plan, and if you’re dragging your feet, there’s no excuse good enough for me.”

Last year, King filed a slew of bills in response to the devastating Smokehouse Creek wildfires in the Texas Panhandle and parts of Oklahoma in 2024. It was the largest wildfire in Texas history, started when a decayed power pole owned by Xcel Energy snapped and landed in dry grass.

It was one of a spate of fires, the majority of which were linked to electrical ignitions.

This year alone has been a very active wildfire season. Nim Kidd, chief for the Texas Division of Emergency Management, said the state has helped local governments respond to more than 1,200 fires since the start of the year. The Ross Fire, which burned for more than three weeks in North Texas, was finally contained by firefighters last week. It’s now the second largest wildfire in the region’s history.

Two wildfires have broken out on Craig Cowden’s Panhandle ranch this year, both ignited by electrical equipment used by oil and gas companies. Cowden extinguished them, before they could spread beyond 5 acres — a fraction of the 20,000 acres he lost to wildfires in 2024.

Cowden was one of many ranchers who worked with lawmakers last year to address the problem. Over the years, several fires have started on Cowden’s land, most of which were the result of faulty or damaged electrical equipment.

“It’s kind of discouraging that there hasn’t been more proactively submitting their wildfire plan,” Cowden said.

Slow progress

There has been progress since the bill was filed. According to King, six fires have been linked to electrical issues this year, a significant decrease from 80 in 2024.

Connie Corona, director at the PUC, explained the lag in filings to lawmakers, stating that on top of the eight who have submitted, four more have given the PUC a date for when they intend to file their plans. Corona said another 135 have indicated to the PUC they are in the process of preparing their plan. This leaves 13 who have not communicated their plans to the PUC.

“We’ve asked for a heads-up notice of when the utility plans to file, and try to ensure that meets with the resources we have available,” Corona told lawmakers.

Corona said PUC staff had created a model wildfire mitigation plan that utility companies can use as a template. The model is intended to support smaller utility companies that lack sufficient resources to make their own plan. King asked Corona for a list of entities who complied with the requirement.

“When eight out of 160 have complied, and we’re sitting here in September, that doesn’t sound like a very good response to me,” King said.

A looming deadline

Brad Baldridge, interim president of Southwestern Public Service Company, which operates as Xcel Energy, told lawmakers what his company is doing to mitigate wildfires. The company was heavily criticized in the wake of the fires and has since deployed 97 wildfire detection cameras across its service territory. The cameras use AI to detect smoke and provide that information in real-time to utility personnel, local fire responders and emergency managers. It also uses Public Safety Power Shutoffs to turn off power in certain areas during critical wildfire conditions to prevent an electrical start. Baldridge said since 2024, the company has had to shut off power five times.

When King asked if the company had submitted its wildfire mitigation plans, Baldridge said it was submitted last month. It would have been submitted earlier, he said, but there was “tremendous” vegetation that grew from rain earlier in the year.

“All of our experts were focusing on wildfire mitigation,” Baldridge said. “Which delayed us a little bit in our filing.”

Mark Bell, CEO for the Association of Electric Companies of Texas, said they are using remote cameras and sensors to detect wildfires and are taking a more aggressive approach to manage vegetation. They also use power shutoffs in extreme conditions to minimize the risk. Bell testified that their utility companies were on track to file their wildfire mitigation plans.

“I think all the plans are going to be filed by the end of the year,” Bell said.

King reminded Bell that it’s September, and many haven’t filed yet.

“That’d be 148 (plans) approved before January,” King said.

Bell assured King that five of them have filed their plans and one is scheduled to file in October.

Corona, with the PUC, said there are also pole and maintenance plans due in January that will detail a complete inventory of those assets owned by utilities. King said the plan is to have the companies list everything they own in Texas, where it is and how old it is. However, he said they aren’t being compliant and lawmakers will see what happens in January.

Cowden, the rancher in the Panhandle, told the Tribune that while it’s not technically fire season anymore, there are still small fires that ignite around the area.

Cowden sees the amount of work being done by Xcel Energy to upgrade their electrical poles and infrastructure in the area. He said it’s different than before the wildfires in 2024. He thinks the fires got their attention.

“You can tell they’re making a conscious effort to try to upgrade their infrastructure,” Cowden said.

__

This story was originally published by The Texas Tribune and distributed through a partnership with The Associated Press.