data demands

Meta and OpenAI agree to follow Texas’ new standards for data centers

Meta's El Paso data center. Image via atmeta.com

Meta Platforms, the parent company of Facebook and Instagram; OpenAI, the owner of ChatGPT; and other tech companies have agreed to follow Texas’ new standards for the development of data centers.

As Texas politicians respond to communities’ increased pushback against power- and water-dependent data centers, Gov. Greg Abbott recently established guidelines for data center projects. President Trump and Gina Jinojosa, a Democrat who will oppose Abbott in the November election, have leveled criticism about the new rules.

Abbott recently directed the Public Utility Commission of Texas and Electric Reliability Council of Texas (ERCOT) to ensure data centers:

  • Pay for their electrical infrastructure instead of shifting costs to families and small businesses
  • Reuse their own water
  • Reduce the cost of electricity for Texans
  • Prevent disruption to residential neighborhoods
  • Eliminate reliance on taxpayer-funded financial incentives

Abbott and Trump differ over data center ‘guardrails’

After releasing the guidelines, Abbott put a moratorium on new data centers in the state.

Abbott directed the Public Utility Commission and ERCOT to audit all data center projects going through ERCOT’s approval process for connecting to the state’s power grid. The two agencies must complete their review before a data center project can join the grid. Any project that fails to comply with the agencies’ requirements won’t be permitted access to the grid.

“I established clear guardrails to ensure data centers protect our electric grid, conserve our water, respect our neighborhoods, and pay their own way,” Abbott, who’s running for a fourth consecutive term as governor, said in a news release. “They must not pass costs on to Texas families or interfere with their quality of life.”

Abbott has hailed Texas as “the epicenter of AI development.”

In a recent interview with Punchbowl News, President Trump questioned the data center rules imposed by Abbott, a fellow Republican.

“I saw Texas the other day sort of is against data centers,” Trump said. “I think it’s a mistake. And I’m not taking positions, I just think it’s a mistake, because there are other communities that want it. When a community wants it, it means a lot of money is going to come into that community.”

In a statement, Gina Hinojosa, the Democratic nominee for Texas governor, stresses that the governor’s data center standards don’t wield the same power that laws would.

“We need a moratorium on data centers until the legislature can meet to put in place real protections so Texans can have a seat at the table to decide if and how data centers come into their communities,” Hinojosa said. “When the companies being regulated are cheering for the rules, you know the rules were written for them, not for Texans.”

The Texas Tribune has identified at least 248 planned data centers in the state, with perhaps hundreds more that aren’t as far along in the development process. At least 355 data centers already operate in Texas. The majority of the new data centers will help power AI software and services.

Meta promises it will be ‘paying our own way‘

In a blog post, Meta commends Abbott’s data center initiative. Meta and investment manager BlackRock are investing more than $10 billion to build a data center campus in El Paso. The 12-building campus, expected to go online in 2028, will be capable of delivering 1 gigawatt of computing power to support Meta’s AI technology.

BlackRock will own 80 percent of the project, and Meta will own the remaining 20 percent.

Meta’s two other Texas data centers are in Fort Worth and Temple.

“Whether it’s creating jobs, growing opportunities for local businesses, or improving energy and water infrastructure, we’re committed to strengthening communities and paying our own way,” Meta says of Abbott’s directive.

OpenAI commits to helping Texas maintain AI leadership

In an Aug. 7 letter to Abbott, OpenAI says it, too, will follow Texas’ data center standards. In fact, the company says the standards reflect practices it already applies to data center projects.

“Texas has built a strong environment for innovation, energy, and economic growth,” the company says. “OpenAI wants to help Texas remain a national leader in AI while demonstrating that this growth can be responsible, reliable, and beneficial to Texans.”

OpenAI is building a $470 million data center in Milam County, and last year it launched operations at a data center campus in Abilene as part of its $500 billion Stargate initiative with Oracle and SoftBank.

Abbott’s office also announced Aug. 11 that EdgeConneX and Stream Data Centers have also pledged to comply with the regulations. Read more here.

Trending News

A View From HETI

The permit is the first issued for a high-temperature gas-cooled nuclear reactor in nearly 60 years. Photo courtesy X-energy

The federal government has given preliminary approval for construction of four nuclear reactors at a Dow site on the Texas Gulf Coast.

The U.S. Nuclear Regulatory Commission (NRC) recently signed off on a permit for Dow and Maryland-based nuclear reactor developer X-energy to build Long Mott Generating Station at Dow’s Seadrift complex. The complex is near Port Lavaca and about 140 miles southwest of Houston.

The NRC issued the permit but hasn’t yet authorized construction to start. The commission said it’s the first construction permit issued for a high-temperature gas-cooled nuclear reactor in nearly 60 years.

Edward Stones, vice president of Dow’s energy and climate business, said the permit approval represents “another important milestone” for Long Mott. It’s expected to be the first-ever advanced nuclear project at a North American industrial site.

Construction at Long Mott could begin before 2030.

Dow’s Seadrift complex manufactures chemicals and plastics. The roughly 4,700-acre site employs more than 1,200 people. Union Carbide, a Dow subsidiary, operates the parent company’s second-largest facility in Texas.

Long Mott will supply zero-carbon electricity and high-temperature steam at Seadrift, replacing current energy- and steam-generating methods. Dow and X-energy are developing the project with support from the U.S. Department of Energy’s Advanced Reactor Demonstration Program.

Mike Goff, principal deputy assistant secretary for nuclear energy, said the NRC’s approval “demonstrates meaningful progress toward deploying advanced reactors that can deliver reliable power and industrial heat, strengthen American energy leadership and expand the role of nuclear energy in meeting our nation’s growing energy demands.”

Plans call for four small X-energy modular reactors to operate at Long Mott. Each reactor would be capable of producing 80 megawatts of electricity or 200 megawatts of thermal energy. Initial delivery of energy could happen as soon as the early 2030s.

“Advanced nuclear has attractive advantages over other sources of clean power, including a compact footprint, competitive cost, and enhanced power and steam reliability,” said Jim Fitterling, executive chair of Dow.