The grant will support power substation upgrades in the Houston area. Photo via Getty Images

A $50 million federal grant will help Houston-based CenterPoint Energy strengthen Houston’s power grid.

The U.S. Department of Energy (DOE) grant will support power substation upgrades in the Houston area.

“Our mission is to build the most resilient coastal grid in the nation for the 2.9 million customers we proudly serve in the greater Houston area … [The grant] will directly fund industry-leading technology improvements that are expected to strengthen resiliency, reliability, and meet the growing energy needs of our region,” Jason Ryan, CenterPoint Energy’s executive vice president for regulatory services and government affairs, said in a release.

CenterPoint says the project will make it one of the first U.S. utilities to install Siemens Energy’s grid-stabilizing technology.

The project will create more than 500 construction and installation jobs, CenterPoint says.

“Generations of CenterPoint customers and families in the region will benefit from the advanced technology this grant is funding,” said Kathleen Jackson, a member of the Public Utility Commission of Texas. “And any time companies make improvements like this to their systems, the long-term impact is making the entire grid stronger for Texans.”

The $176.7 million substation project is part of CenterPoint’s Greater Houston Resiliency Initiative, which launched in 2024.

So far, the initiative has:

  • Installed nearly 82,400 storm-resilient poles and equipment
  • Trimmed and cleared more than 13,700 miles of trees and vegetation near power lines
  • Added nearly 820 grid automation and intelligence devices
  • Put more than 880 miles of power lines underground

The initiative kicked off three years after Winter Storm Uri. CenterPoint received harsh criticism for what customers complained was the utility’s slow response to the 2021 storm. Uri caused a massive power outage and at least 246 deaths across Texas.

CenterPoint blamed the Electric Reliability Council of Texas (ERCOT), which operates the power grid for most Texans, for not supplying the utility with enough electricity during and after the storm.

Residents in Montgomery, Liberty and Hardin counties can expect to see power grid improvements in the coming years. Photo via Getty Images

Texas awards $73M for Houston-area grid resilience project

grid funding

Texas Gov. Gregg Abbott announced millions in funding for energy resilience projects around this state this week, with one major project set to impact the greater Houston area.

As part of the Texas Energy Fund's Outside of ERCOT Grant Program, the state announced a roughly $73 million agreement with the Sam Houston Electric Cooperative to replace and upgrade more than 9,000 electric poles and improve other equipment in Montgomery, Liberty and Hardin counties. The agreement is the first for the fund's Outside of ERCOT Grant Program, which supports state projects outside of the state's largest grid.

The multibillion-dollar Texas Energy Fund aims to "finance the construction, maintenance, and modernization of electric facilities across Texas." It was approved by voters in 2023. Other programs within the fund include the:

  • In-ERCOT Generation Loan Program
  • Completion Bonus Grant Program
  • Texas Backup Power Package Program

“The Texas Energy Fund delivers real results for Texans and strengthens the electric systems that families, businesses, and communities depend on,” Abbott said in a news release. “This grant to Sam Houston Electric Cooperative will replace thousands of vulnerable utility poles to better withstand severe weather and ensure a more reliable and resilient grid in East Texas.”

The Houston-area project, nicknamed Steel Anchor, is expected to be completed by June 2031. According to the release from the governor's office, the Sam Houston Electric Cooperative’s territory is one of the most hurricane-prone service areas in the state. The cooperative serves more than 38,000 Texas consumers

“Over the past decade, Sam Houston EC has strategically replaced poles to improve the strength of its electricity distribution system. This grant will boost the Cooperative’s ongoing grid-hardening and resiliency program,” Doug Turk, CEO of the Sam Houston Electric Cooperative, added in the release.

Following the announcement of the Sam Houston funding, Abbott's office also awarded another $200 million from the Outside of ERCOT Grant Program to upgrade approximately 700 miles of power equipment in Northeast Texas. The equipment is operated by Southwestern Electric Power Company, which serves more than 192,000 Texas consumers. The project will include improvements to 200 circuits, replacing aging copper wire with aluminum alloy conductors and replacing existing utility poles.

Additionally, the state announced its seventh Texas Energy Fund loan agreement for a 570 megawatt natural gas power plant in Sherman, Texas. The 20-year loan of up to $411 million is between the Public Utility Commission of Texas and Rayburn Electric Cooperative and is part of the fund's In-ERCOT Generation Loan Program. Rayburn will build the facility near its existing Rayburn Energy Station 1 in the Texoma region. It will connect to the ERCOT North Load Zone.

“When Texas voters overwhelmingly approved the Texas Energy Fund, they gave us a mandate to secure new, reliable power generation for Texas,” PUCT Chairman Thomas Gleeson added in a release. “The TxEF is delivering on that promise, and Rayburn Electric Cooperative’s new 570 MW power plant is proof. We are ensuring Texas families and businesses have power they can depend on for years to come.”

The Woodlands-based Lancium has licensed patents to ERCOT that help increase or decrease power consumption during peak periods or emergencies. Photo courtesy of ERCOT

Woodlands company licenses free patents to ERCOT to boost grid reliability

grid deal

Lancium, a company based in The Woodlands that specializes in infrastructure for connecting large-scale data centers to power grids, is licensing a portfolio of patents to the Electric Reliability Council of Texas (ERCOT) at no cost.

In a news release, Lancium says the intellectual property agreement “ensures ERCOT can sublicense these patents freely, thereby expanding market participation opportunities without risk of patent infringement disputes.”

“This agreement exemplifies Lancium’s dedication to supporting grid stability and innovation across the ERCOT region,” Michael McNamara, CEO of Lancium, said in a news release. “While these patents represent significant technological advancements, we believe that enabling ERCOT and its market participants to operate freely is more valuable for the long-term reliability and resilience of the Texas grid.”

The licensed patents encompass Lancium technologies that support load resources in ERCOT’s market, which covers about 90 percent of Texas. Specifically, the patents deal with controllable load resources. A controlled load resource allows ERCOT and other grids to increase or decrease power consumption during peak periods or emergencies.

ERCOT predicts power demand in Texas will nearly double by 2030, “in part due to more requests to plug into the grid from large users like data centers, crypto mining facilities, hydrogen production plants, and oil and gas companies,” The Texas Tribune reported.

CenterPoint Energy aims to complete its suite of grid resiliency projects before the 2025 hurricane season. Photo via centerpointenergy.com

CenterPoint reports progress on grid improvements ahead of 2025 hurricane season

grid resilience

As part of an ongoing process to make Houston better prepared for climate disasters, CenterPoint Energy announced its latest progress update on the second phase of the Greater Houston Resiliency Initiative (GHRI).

CenterPoint reported that it has completed 70 percent of its resiliency work and all GHRI-related actions are expected to be complete before the official start of the 2025 hurricane season.

"Our entire CenterPoint Houston Electric team is focused on completing this historic suite of grid resiliency actions before the start of hurricane season,” Darin Carroll, Senior Vice President of CenterPoint's Electric Business, said in a news release. “That is our goal, and we will achieve it. To date, we have made significant progress as part of this historic effort.”

CenterPoint’s resiliency solutions include clearing higher-risk vegetation across thousands of miles of power lines, adding thousands more automation devices capable of self-healing, installing thousands of storm-resistant poles, and undergrounding hundreds of miles of power lines.

CenterPoint's GHRI efforts, which entered a second phase in September 2024, aim to improve overall grid resiliency and reliability and are estimated to reduce outages for customers by more than 125 million minutes annually, according to the company. It has undergrounded nearly 350 miles of power lines, about 85 percent of the way toward its target of 400 miles, which will help improve resiliency and reduce the risk of outages. CenterPoint also aims to install the first of 100 new local weather monitoring stations by June 1.

In March, CenterPoint cleared 655 miles of high-risk vegetation near power lines, installed 1,215 automated reliability devices capable of self-healing, and added an additional 3,300 storm-resilient poles.

In April, CenterPoint will begin building a network of 100 new weather monitoring stations, which will provide 24/7 weather monitoring and storm response preparation.

“We will continue to work every day to complete these critical improvements as part of our company's goal of building the most resilient coastal grid in the country,” Carroll added in the release.

Georg Rute ,CEO of Gridraven, discusses the potential of AI and DLR. Photo via Getty Images

Energy expert: Unlocking the potential of the Texas grid with AI & DLR

guest column

From bitter cold and flash flooding to wildfire threats, Texas is no stranger to extreme weather, bringing up concerns about the reliability of its grid. Since the winter freeze of 2021, the state’s leaders and lawmakers have more urgently wrestled with how to strengthen the resilience of the grid while also supporting immense load growth.

As Maeve Allsup at Latitude Media pointed out, many of today’s most pressing energy trends are converging in Texas. In fact, a recent ERCOT report estimates that power demand will nearly double by 2030. This spike is a result of lots of large industries, including AI data centers, looking for power. To meet this growing demand, Texas has abundant natural gas, solar and wind resources, making it a focal point for the future of energy.

Several new initiatives are underway to modernize the grid, but the problem is that they take a long time to complete. While building new power generation facilities and transmission lines is necessary, these processes can take 10-plus years to finish. None of these approaches enables both significantly expanded power and the transmission capacity needed to deliver it in the near future.

Beyond “curtailment-enabled headroom”

A study released by Duke University highlighted the “extensive untapped potential” in U.S. power plants for powering up to 100 gigawatts of large loads “while mitigating the need for costly system upgrades.” In a nutshell: There’s enough generating capacity to meet peak demand, so it’s possible to add new loads as long as they’re not adding to the peak. New data centers must connect flexibly with limited on-site generation or storage to cover those few peak hours. This is what the authors mean by “load flexibility” and “curtailment-enabled headroom.”

As I shared with POWER Magazine, while power plants do have significant untapped capacity, the transmission grid might not. The study doesn’t address transmission constraints that can limit power delivery where it’s needed. Congestion is a real problem already without the extra load and could easily wipe out a majority of that additional capacity.

To illustrate this point, think about where you would build a large data center. Next to a nuclear plant? A nuclear plant will already operate flat out and will not have any extra capacity. The “headroom” is available on average in the whole system, not at any single power plant. A peaking gas plant might indeed be idle most of the time, but not 99.5% of the time as highlighted by the Duke authors as the threshold. Your data center would need to take the extra capacity from a number of plants, which may be hundreds of miles apart. The transmission grid might not be able to cope with it.

However, there is also additional headroom or untapped potential in the transmission grid itself that has not been used so far. Grid operators have not been able to maximize their grids because the technology has not existed to do so.

The problem with existing grid management and static line ratings

Traditionally, power lines are given a static rating throughout the year, which is calculated by assuming the worst possible cooling conditions of a hot summer day with no wind. This method leads to conservative capacity estimates and does not account for environmental factors that can impact how much power can actually flow through a line.

Take the wind-cooling effect, for example. Wind cools down power lines and can significantly increase the capacity of the grid. Even a slight wind blowing around four miles per hour can increase transmission line capacity by 30 percent through cooling.

That’s why dynamic line ratings (DLR) are such a useful tool for grid operators. DLR enables the assessment of individual spans of transmission lines to determine how much capacity they can carry under current conditions. On average, DLR increases capacity by a third, helping utilities sell more power while bringing down energy prices for consumers.

However, DLR is not yet widely used. The core problem is that weather models are not accurate enough for grid operators. Wind is very dependent on the detailed landscape, such as forests or hills, surrounding the power line. A typical weather forecast will tell you the average conditions in the 10 square miles around you, not the wind speed in the forest where the power line is. Without accurate wind data at every section, even a small portion of the line risks overheating unless the line is managed conservatively.

DLR solutions have been forced to rely on sensors installed on transmission lines to collect real-time weather measurements, which are then used to estimate line ratings. However, installing and maintaining hundreds of thousands of sensors is extremely time-consuming, if not practically infeasible.

The Elering case study

Last year, my company, Gridraven, tested our machine learning-powered DLR system, which uses a AI-enabled weather model, on 3,100 miles of 110-kilovolt and 330-kilovolt lines operated by Elering, Estonia’s transmission system operator, predicting ratings in 15,000 individual locations. The power lines run through forests and hills, where conventional forecasting systems cannot predict conditions with precision.

From September to November 2024, our average wind forecast accuracy saw a 60 percent improvement over existing technology, resulting in a 40 percent capacity increase compared to the traditional seasonal rating. These results were further validated against actual measurements on transmission towers.

This pilot not only demonstrated the power of AI solutions against traditional DLR systems but also their reliability in challenging conditions and terrain.

---

Georg Rute is the CEO of Gridraven, a software provider for Dynamic Line Ratings based on precision weather forecasting available globally. Prior to Gridraven, Rute founded Sympower, a virtual power plant, and was the head of smart grid development at Elering, Estonia's Transmission System Operator. Rute will be onsite at CERAWeek in Houston, March 10-14.

The views expressed herein are Rute's own. A version of this article originally appeared on LinkedIn.

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Fervo Energy adds transmission capacity at Cape Station geothermal project

geothermal expansion

Houston-based geothermal power company Fervo Energy has expanded its deal with Longroad Energy for transmission of electricity generated by Fervo’s Utah project.

Fervo added 105 megawatts to its existing 400-megawatt transmission deal with Longroad Energy, a Boston company that develops solar, wind and battery storage projects. The updated agreement will enable Fervo to deliver 505 megawatts of power from its marquee Cape Station geothermal project in Beaver County, Utah.

Dawn Owens, senior vice president of commercial markets at Fervo, said in a release that the new agreement brings another “105 megawatts of long-term, reliable capacity to the grid.”

Subject to regulatory approvals, the new agreement is expected to take effect in 2028.

“Longroad has worked alongside Fervo since its first efforts in Beaver County, and we’re excited to collaborate again,” Charles Spiliotis, chief development officer at Longroad, added in the release. “Providing transmission service for this next phase helps deliver clean, around-the-clock power to the grid.”

Cape Station recently began delivering carbon-free power. Capacity is on track to reach 100 megawatts in early 2027. The project’s second phase is targeted for completion in 2028. It will add 400 megawatts of capacity and is currently under construction.

Cape Station is adjacent to the U.S. Department of Energy’s Frontier Observatory for Research in Geothermal Energy and near the Blundell geothermal power plant.

Earlier this month, Tim Latimer, Fervo’s co-founder, chair, president and CEO, told Wall Street analysts the company had a $11.9 billion backlog of orders in the third quarter, up from $7.2 billion in the previous quarter.

Fervo signed the largest purchase agreement in its history in September with Google. The tech giant agreed to purchase 396 megawatts of geothermal power from Fervo with an option for Google to expand capacity to 1 gigawatt by June 2030. Financial terms weren’t disclosed.

Regulators OK Dow’s Gulf Coast nuclear reactor project

going nuclear

The federal government has given preliminary approval for construction of four nuclear reactors at a Dow site on the Texas Gulf Coast.

The U.S. Nuclear Regulatory Commission (NRC) recently signed off on a permit for Dow and Maryland-based nuclear reactor developer X-energy to build Long Mott Generating Station at Dow’s Seadrift complex. The complex is near Port Lavaca and about 140 miles southwest of Houston.

The NRC issued the permit but hasn’t yet authorized construction to start. The commission said it’s the first construction permit issued for a high-temperature gas-cooled nuclear reactor in nearly 60 years.

Edward Stones, vice president of Dow’s energy and climate business, said the permit approval represents “another important milestone” for Long Mott. It’s expected to be the first-ever advanced nuclear project at a North American industrial site.

Construction at Long Mott could begin before 2030.

Dow’s Seadrift complex manufactures chemicals and plastics. The roughly 4,700-acre site employs more than 1,200 people. Union Carbide, a Dow subsidiary, operates the parent company’s second-largest facility in Texas.

Long Mott will supply zero-carbon electricity and high-temperature steam at Seadrift, replacing current energy- and steam-generating methods. Dow and X-energy are developing the project with support from the U.S. Department of Energy’s Advanced Reactor Demonstration Program.

Mike Goff, principal deputy assistant secretary for nuclear energy, said the NRC’s approval “demonstrates meaningful progress toward deploying advanced reactors that can deliver reliable power and industrial heat, strengthen American energy leadership and expand the role of nuclear energy in meeting our nation’s growing energy demands.”

Plans call for four small X-energy modular reactors to operate at Long Mott. Each reactor would be capable of producing 80 megawatts of electricity or 200 megawatts of thermal energy. Initial delivery of energy could happen as soon as the early 2030s.

“Advanced nuclear has attractive advantages over other sources of clean power, including a compact footprint, competitive cost, and enhanced power and steam reliability,” said Jim Fitterling, executive chair of Dow.

Woodlands startup Mavria raises $130M to mass-produce AI data centers

seed funding

The Woodlands-based Mavria, which mass-produces factory-built modular AI data centers, just emerged from stealth mode with $130 million in funding at a $1 billion valuation.

Mavria raised the money in pre-seed and seed rounds led by Paradigm, an investment firm that concentrates on early-stage startups developing “pioneer” technology. Participants in the funding rounds include AMP PBC, Critical Frontier, Dream Ventures and Liquid 2 Ventures, co-founded by former NFL quarterback Joe Montana.

The company’s inaugural product, Terrain, is a prefabricated data center designed for AI labs, cloud computing providers and data center developers. Mavria says its platform avoids ground-up construction, delivering infrastructure more quickly and at a lower cost.

Mavria tells the Wall Street Journal that the first Terrain unit is being built at a Houston-area factory. The 5-megawatt Terrain system features power distribution, direct liquid cooling, controls and server racks.

“America sets the pace at the intelligence frontier. But the race is moving from the lab into the physical world,” Adam Blake, co-founder and CEO of Mavria, wrote in a blog post.

“Intelligence needs data centers. Data centers need power. Power needs factories, equipment, supply chains, and skilled workers, but much of that infrastructure is still built one custom project at a time, on timelines measured in years.”

Blake and Mavria’s two other co-founders, Nick Poradek and Seth Cohen, most recently worked at the U.S. Department of Energy. There, they focused on reforming the nuclear power sector.

From start to finish, it can take roughly three to six years to build a data center at an estimated cost of $10 million to $37 million per megawatt. Based on those figures, a 100-megawatt data center might cost as much as $3.7 billion.

Here are brief bios of Blake, Poradek and Cohen, who co-founded Mavria in May.

Adam Blake

Blake most recently was a senior advisor to U.S. Energy Secretary Chris Wright. He is co-founder and former CEO of Zego, a provider of energy management technology for property managers. Zego spun out from Brightergy, a commercial solar company. Blake is founder and former CEO of Brightergy.

Nick Poradek

Poradek, chief operating officer at Mavria, was also an advisor to the U.S. energy secretary. He is founder and former CEO of Spring-based Edera Energy, co-founder of The Woodlands-based craft-ice brand Clarity Ice, and founder and former CEO of The Woodlands-based Edera Capital. Poradek sold Edera Energy, a manufacturer of oilfield equipment, to Liberty Energy, a fracking company. Wright is Liberty’s founder and former chairman and CEO.

Seth Cohen

Cohen, chief strategy officer and chief legal officer at Mavria, was head of nuclear law and policy at the Department of Energy. He is also a former NASA advisor and a former attorney at Kirkland & Ellis.

“We believe in rapidly deploying infrastructure as a product, rather than custom-building every project,” Blake said. “We’re bringing together engineering, manufacturing, supply chains and capital so that every project makes us better at delivering the next.”

---

This article originally appeared on our sister site, InnovationMap.