Greentown Houston is asking its current and potential members what they want in a wet lab. Photo via GreentownLabs.com

Greentown Houston has announced it's building a new wet lab facility, and the organization is looking for feedback from its community.

Greentown Labs, which is dual located at their headquarters in Somerville, Massachusetts, and in the Ion District in Houston, has announced earlier this summer that they are building out a wet lab in their Midtown space.

"We have heard from several startups as well as corporate partners in the ecosystem that are looking for wet lab space," says Lara Cottingham, vice president of strategy, policy, and climate impact at Greentown Labs. "Greentown has experience running wet labs from our location in Somerville. We're excited to be able to offer wet lab space to climatetech startups as an additional amenity to the Ion District.

Although Greentown's Boston-area location has wet lab space, Cottingham says the organization is not interested in copying and pasting that same facility. Greentown wants to provide the tools that the Houston ecosystem needs, and that requires getting feedback from its current and potential members.

"We want to announce to the community that this is something we're going to build — but we still need a lot of feedback and input from startups so we can learn what exactly they need or want to see from the wet lab," Cottingham tells InnovationMap. "No two wet labs are the same."

There currently aren't any details available about timeline or specifics of the new facility. Greentown is prioritizing getting feedback from its members and having conversations with potential sponsors and corporate partners.

"Corporate partners are a big part of the ecosystem and the community at Greentown. They can be so many things to our startups — mentors, customers, investors," Cottingham says. "And in this space, they can help us sponsor and financially support the wet lab. We're still fundraising — we have some partners that have committed to funding, but we're still looking for more funding."

In addition to monetary contribution, Cottingham says they are looking for other options as well, from partnerships with equipment providers, hazardous materials management, and more.

Startups that need wet lab space are encouraged to fill out the online form, which will be open through the summer, and potential corporate partners can express their interest online as well.

Greentown Houston opened its doors in 2021 and has since grown to house more than 75 energy and climatetech startups, as well as several accelerators, thanks to support from dozens of corporate partners.

------

This article originally ran on InnovationMap.

EnergyTech Startups, a podcast co-hosted by two Houston clean energy experts, exists to shine a spotlight on innovative companies and Houston as a hub for energy transition businesses. Photo via Unsplash

Houston podcasters aim to showcase promising local energy tech startups

broadcasting innovation

Houston has a bit of a perception problem, according to Jason Ethier, a long-time energy tech innovator and new podcast host.

"Houston isn't viewed as a cool place to build a company if you don't know how good it is to be here," he says on the Houston Innovators Podcast.

Ethier, who serves as senior director of membership at Greentown Labs, set out to fix that when he launched the EnergyTech Startups podcast last fall with co-host Lara Cottingham, the vice president of strategy, policy, and climate impact at Greentown Labs. To date, the show has introduced listeners to over 20 energy founders and is continuing to do so on a biweekly basis.

"As an entrepreneur, sometimes you feel a gap in the market in your bones and you just have to do something about it," Ethier explains on the origin of the show.

Jason Ethier and Lara Cottingham co-host the EnergyTech Startups podcast. Photos courtesy

With his background in the Northeast, Ethier has seen first hand how Houstonians are just different — they tackle tough challenges and are heads-down focused on these innovations.

"Houston has a lot going for it as a place to build a business, and we're not going to do it the Silicon Valley. We do things the Houston way — we build new technologies, we build big projects," Ethier says. "The funny thing about Houstonians I find is that they are very understated with what they achieve and accomplish like it's no big deal. But it is a big deal."

That's where Ethier and the podcast can help shine a spotlight on the unique innovation these startup founders are in the process of commercializing.

"The premise of EnergyTech Startups is that we're building an energy ecosystem here, and energy and climate are two sides of the same coin," he says. "People working on these energy technologies made the choice to come to Houston — they made the choice not to go to Silicon Valley or Boston."

The goal is twofold — give these startups the platform to tell their story and showcase Houston as the hub for energy innovation.

"How do we tell this Houston story so that whenever folks look at the map and say, 'where do I want to build my business?' they look at Houston and see it as a place they should end up," he says.

Listen to the full episode of the Houston Innovators Podcast with Jason Ethier.

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Regulators OK Dow’s Gulf Coast nuclear reactor project

going nuclear

The federal government has given preliminary approval for construction of four nuclear reactors at a Dow site on the Texas Gulf Coast.

The U.S. Nuclear Regulatory Commission (NRC) recently signed off on a permit for Dow and Maryland-based nuclear reactor developer X-energy to build Long Mott Generating Station at Dow’s Seadrift complex. The complex is near Port Lavaca and about 140 miles southwest of Houston.

The NRC issued the permit but hasn’t yet authorized construction to start. The commission said it’s the first construction permit issued for a high-temperature gas-cooled nuclear reactor in nearly 60 years.

Edward Stones, vice president of Dow’s energy and climate business, said the permit approval represents “another important milestone” for Long Mott. It’s expected to be the first-ever advanced nuclear project at a North American industrial site.

Construction at Long Mott could begin before 2030.

Dow’s Seadrift complex manufactures chemicals and plastics. The roughly 4,700-acre site employs more than 1,200 people. Union Carbide, a Dow subsidiary, operates the parent company’s second-largest facility in Texas.

Long Mott will supply zero-carbon electricity and high-temperature steam at Seadrift, replacing current energy- and steam-generating methods. Dow and X-energy are developing the project with support from the U.S. Department of Energy’s Advanced Reactor Demonstration Program.

Mike Goff, principal deputy assistant secretary for nuclear energy, said the NRC’s approval “demonstrates meaningful progress toward deploying advanced reactors that can deliver reliable power and industrial heat, strengthen American energy leadership and expand the role of nuclear energy in meeting our nation’s growing energy demands.”

Plans call for four small X-energy modular reactors to operate at Long Mott. Each reactor would be capable of producing 80 megawatts of electricity or 200 megawatts of thermal energy. Initial delivery of energy could happen as soon as the early 2030s.

“Advanced nuclear has attractive advantages over other sources of clean power, including a compact footprint, competitive cost, and enhanced power and steam reliability,” said Jim Fitterling, executive chair of Dow.

Woodlands startup Mavria raises $130M to mass-produce AI data centers

seed funding

The Woodlands-based Mavria, which mass-produces factory-built modular AI data centers, just emerged from stealth mode with $130 million in funding at a $1 billion valuation.

Mavria raised the money in pre-seed and seed rounds led by Paradigm, an investment firm that concentrates on early-stage startups developing “pioneer” technology. Participants in the funding rounds include AMP PBC, Critical Frontier, Dream Ventures and Liquid 2 Ventures, co-founded by former NFL quarterback Joe Montana.

The company’s inaugural product, Terrain, is a prefabricated data center designed for AI labs, cloud computing providers and data center developers. Mavria says its platform avoids ground-up construction, delivering infrastructure more quickly and at a lower cost.

Mavria tells the Wall Street Journal that the first Terrain unit is being built at a Houston-area factory. The 5-megawatt Terrain system features power distribution, direct liquid cooling, controls and server racks.

“America sets the pace at the intelligence frontier. But the race is moving from the lab into the physical world,” Adam Blake, co-founder and CEO of Mavria, wrote in a blog post.

“Intelligence needs data centers. Data centers need power. Power needs factories, equipment, supply chains, and skilled workers, but much of that infrastructure is still built one custom project at a time, on timelines measured in years.”

Blake and Mavria’s two other co-founders, Nick Poradek and Seth Cohen, most recently worked at the U.S. Department of Energy. There, they focused on reforming the nuclear power sector.

From start to finish, it can take roughly three to six years to build a data center at an estimated cost of $10 million to $37 million per megawatt. Based on those figures, a 100-megawatt data center might cost as much as $3.7 billion.

Here are brief bios of Blake, Poradek and Cohen, who co-founded Mavria in May.

Adam Blake

Blake most recently was a senior advisor to U.S. Energy Secretary Chris Wright. He is co-founder and former CEO of Zego, a provider of energy management technology for property managers. Zego spun out from Brightergy, a commercial solar company. Blake is founder and former CEO of Brightergy.

Nick Poradek

Poradek, chief operating officer at Mavria, was also an advisor to the U.S. energy secretary. He is founder and former CEO of Spring-based Edera Energy, co-founder of The Woodlands-based craft-ice brand Clarity Ice, and founder and former CEO of The Woodlands-based Edera Capital. Poradek sold Edera Energy, a manufacturer of oilfield equipment, to Liberty Energy, a fracking company. Wright is Liberty’s founder and former chairman and CEO.

Seth Cohen

Cohen, chief strategy officer and chief legal officer at Mavria, was head of nuclear law and policy at the Department of Energy. He is also a former NASA advisor and a former attorney at Kirkland & Ellis.

“We believe in rapidly deploying infrastructure as a product, rather than custom-building every project,” Blake said. “We’re bringing together engineering, manufacturing, supply chains and capital so that every project makes us better at delivering the next.”

---

This article originally appeared on our sister site, InnovationMap.

Houston geothermal company lands 50 MW power deal with Google

power purchase

Houston-based geothermal company Quaise Energy has secured a major power purchase agreement from Google.

The companies announced this week that the tech giant would purchase 50 megawatts of superhot geothermal power from Quaise's flagship Project Obsidian geothermal project in Central Oregon starting in 2030. The power will support Google's existing data center campuses in the Dalles region of Oregon, according to a news release.

“We started Quaise to make the Earth's most abundant energy source universally accessible — and this agreement marks a critical next step, not just for Quaise but for the entire clean energy sector," Carlos Araque, CEO and president of Quaise, said in the release. “Together with Google, we are building the commercial foundation for superhot geothermal and cementing the United States as the global leader in geothermal power.”

Google operates three data center campuses in Central Oregon, which have achieved 83 percent carbon-free energy, according to the company. Google says the new partnership with Quaise supports its clean energy efforts.

“Google data centers are long-term investments in the communities we call home,” Lucia Tian, head of advanced energy technologies at Google, added in the release. “This collaboration with Quaise on superhot geothermal will help fuel local economic growth while helping to build a more robust and affordable energy future for Oregon.”

Quaise's Project Obsidian is slated to come online in 2030. Phase I will generate 50 megawatts of geothermal power, with the total capacity planned to reach 1 gigawatt by Phase III. The company says Phase II of the project will be the first to use millimeter wave drilling, which can "plug into existing drilling rigs to economically reach superhot geothermal conditions."

Quaise closed its Series B fundraising round at $180 million in August after inking a $35 million investment from Houston-based Nabors Industries. It previously held a "first close" of the round at $134 million, led by San Francisco-based investment firm Prelude Ventures.

The company announced in March that it was aiming to raise $200 million for Project Obsidian through $100 million in Series B funding, plus an additional $100 million from grants, debt and project-level finance.

Meanwhile, Google struck a giant geothermal deal with Fervo Energy, another Houston-based geothermal leader, in September. Google agreed to purchase 396 megawatts of geothermal power from Fervo with an option for Google to expand capacity to 1 gigawatt by June 2030. The deal represents the largest purchase agreement in Fervo's history.

Financial terms were not disclosed for Google's deal with Quaise or Fervo.