ERCOT has launched its new Grid Research, Innovation, and Transformation (GRIT) initiative to help resolve grid challenges and meet growing demand. Photo via Getty Images

As AI data centers gobble up more electricity, the Electric Reliability Council of Texas (ERCOT) — whose grid supplies power to 90 percent of Texas — has launched an initiative to help meet challenges presented by an increasingly strained power grid.

ERCOT, based in the Austin suburb of Taylor, said its new Grid Research, Innovation, and Transformation (GRIT) initiative will tackle research and prototyping of emerging technology and concepts to “deeply understand the implications of rapid grid and technology evolution, positioning ERCOT to lead in the future energy landscape.”

“As the ERCOT grid continues to rapidly evolve, we are seeing greater interest from industry and academia to collaborate on new tools and innovative technologies to advance the reliability needs of tomorrow’s energy systems,” ERCOT President and CEO Pablo Vegas said in a news release. “These efforts will provide an opportunity to share ideas and bring new innovations forward, as we work together to lead the evolution and expansion of the electric power grid.”

In conjunction with the GRIT initiative, ERCOT launched the Research and Innovation Partnership Engagement (RIPE) program. The program enables partners to work with ERCOT on developing technology aimed at resolving grid challenges.

To capitalize on ideas for grid improvements, the organization will host its third annual ERCOT Innovation Summit on March 31 in Round Rock. The summit “brings together thought leaders across the energy research and innovation ecosystem to explore solutions that use innovation to impact grid transformation,” ERCOT said.

“As the depth of information and industry collaboration evolves, we will continue to enhance the GRIT webpages to create a dynamic and valuable resource for the broader industry to continue fostering strong collaboration and innovation with our stakeholders,” said Venkat Tirupati, ERCOT’s vice president of DevOps and grid transformation.

ERCOT’s GRIT initiative comes at a time when the U.S. is girding for heightened demand for power, due in large part to the rise of data centers catering to the AI boom.

A study released in 2024 by the Electric Power Research Institute (EPRI) predicted electricity for data centers could represent as much as 9.1 percent of total power usage in the U.S. by 2030. According to EPRI, the share of Texas electricity consumed by data centers could climb from 4.6 percent in 2023 to almost 11 percent by 2030.

A report issued in 2024 by the federal government’s Lawrence Berkeley National Laboratory envisions an even faster increase in data-center power usage. The report projected data centers will consume as much as 12 percent of U.S. electricity by 2028, up from 4.4 percent in 2023.

In 2023, the EPRI study estimated, 80 percent of the U.S. electrical load for data centers was concentrated in two states, led by Virginia and Texas. The University of Texas at Austin’s Center for Media Engagement reported in July that Texas is home to 350 data centers, second only to Virginia.

“The U.S. electricity sector is working hard to meet the growing demands of data centers, transportation electrification, crypto-mining, and industrial onshoring, while balancing decarbonization efforts,” David Porter, EPRI’s vice president of electrification and sustainable energy strategy, said. “The data center boom requires closer collaboration between large data center owners and developers, utilities, government, and other stakeholders to ensure that we can power the needs of AI while maintaining reliable, affordable power to all customers.”

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Electric truck charging network expands to Houston-Dallas freight corridor

electric trucking

Greenlane Infrastructure, an electric public charging station developer and operator, is expanding outside of its home state of California and into Texas.

The Santa Monica-based company plans to launch its high-power charging sites along the Dallas–Houston I-45 corridor, which is one of the highest-volume commercial trucking routes in the country, according to a news release from Greenlane.

The sites will feature 6-8 pull-through lanes with chargers supporting combined charging system (CCS) and megawatt charging system (MCS) connectors that allow electric truck drivers to recharge their vehicles during standard rest periods. They will also offer tractor parking and charging, as well as operations that will allow for overnight stops.

Drivers can reserve chargers in advance, monitor charging activity in real time, and manage billing from the Greenlane Edge platform.

“Our customers are making commitments to electrify their fleets, and they need a charging network that can grow alongside them,” Patrick Macdonald-King, CEO of Greenlane, said in the release. “This is the first leg of the Texas triangle, one of the more important freight arteries in the country, so bringing high-power charging there is the next logical step in building a network that serves how freight moves across America.”

Greenlane is also expanding across the West Coast, with five locations under development in California and Nevada. It opened its flagship Greenlane Center in Colton, California, in April 2025. The company plans to open locations in Blythe, California, and Port of Long Beach this year.

Greelane was founded in 2023 as a joint venture between Daimler Truck North America, NextEra Energy Resources and BlackRock. It has secured partnerships with electric long-haul truck developer Windrose Technology, Velocity Truck Centers and Volvo Trucks North America.

Houston startup lands $1B from Blackstone and Halliburton, plans acquisition

power deal

Houston-based power generation startup VoltaGrid has nailed down a $1 billion equity investment from asset management heavyweight Blackstone and Houston-based oilfield services provider Halliburton.

The investment comes in two forms:

  • A $775 million primary capital raise
  • A $225 million secondary capital purchase from existing investors

VoltaGrid, founded in 2020, provides behind-the-meter mobile power generation equipment for data centers, microgrids and industrial customers.

Aside from the $1 billion investment, VoltaGrid has agreed to buy Propell Energy Technology, a VoltaGrid supplier, for an undisclosed amount. Propell offers a natural gas power generation platform for AI data centers. VoltaGrid plans to add two manufacturing plants at Propell’s facilities in Granbury, a Dallas-Fort Worth suburb.

The investment and acquisition deals are expected to close in mid-2026.

Funds managed by Blackstone Tactical Opportunities are contributing to the $1 billion investment. William Nicholson, managing director of Blackstone, called VoltaGrid “a highly differentiated platform addressing one of the most important infrastructure needs of the AI era: reliable, rapidly deployable power. This investment is a strong example of Tac Opps’ focus on providing flexible, scaled capital to exceptional entrepreneurs and businesses operating in Blackstone’s highest-conviction investment themes.”

Nathan Ough, founder and CEO of VoltaGrid, said in a release that the Blackstone investment “is a powerful endorsement of the platform we have built and the role VoltaGrid is playing in delivering the energy infrastructure of the AI era.”

Last October, VoltaGrid and Halliburton said they had forged a partnership to supply power for data centers around the world, with the Middle East picked as the initial target. Two months later, the companies said they had arranged the manufacturing of 400 megawatts of natural gas power systems that’ll be delivered in 2028 to support new data centers in the Eastern Hemisphere.

Jeff Miller, president and CEO of Halliburton, said his company’s investment in VoltaGrid “reflects our shared focus on long-term solutions for the world’s most demanding power environments, and advances VoltaGrid’s ability to deliver reliable, distributed power at scale.”