Woodlands-based Lancium teams up on West Texas data center campus

Lancium Technologies has teamed up on a 1-gigawatt data center campus in Childress County. Photo via Getty Images

The Woodlands-based Lancium Technologies, which designs, develops, and manages gigawatt-scale data center campuses, has teamed up with Denver-based data center builder and operator Crusoe Energy Systems on a new grid-connected campus more than 100 miles east of Wichita Falls.

Construction on the 1-gigawatt Childress County campus, being built for an unidentified tech company, is expected to start in Q3 of this year.

Lancium owns the 270-acre site where the data center campus will be located and will set up and manage the campus’ energy infrastructure. Crusoe will design, build, and operate the campus.

The two companies already are working together on data centers in Abilene. Their first data center has already expanded to a capacity of 1.2 gigawatts, and a 900-megawatt data center is planned for adjacent land owned by Lancium.

The Abilene project is the first site of the Stargate initiative, an AI infrastructure program backed by MGX, OpenAI, Oracle, and Softbank to create a U.S. network of hyperscale AI data centers. The four-year initiative has earmarked $500 billion to build the network.

“Childress is a natural next step in our partnership with Crusoe,” Lancium CEO Michael McNamara said in a news release. “Crusoe has been a great partner to build alongside in Abilene, and we’re glad to bring that same model — and the jobs and investment that come with it — to the community of Childress. We are deeply committed to working with local stakeholders to advance a model of development that addresses the broader needs of the community we will share for a very long time.”

Last year, Lancium appeared at No. 43 on Time and Statista’s list of America’s top greentech companies.

Lancium has raised $1.25 billion in funding since its founding in 2017, according to PitchBook and CB Insights.

In 2021, Lancium closed $150 million in funding led by Hanwha Solutions, with participation from SBI Holdings, Novawulf and other investors. Four years later, the company arranged $600 million in debt financing to advance development of “clean” data center campuses.