The new facility is expected to be one of the largest manufacturing sites for power conversion systems in the U.S. Photo courtesy Power Electronics

Spanish renewable energy company Power Electronics broke ground on its new 53-acre Houston campus on Sept.24.

The new site is expected to create over 400 local jobs and deliver 40 gigawatts of production capacity per year. The company said in a news release that the campus is expected to be the largest manufacturing site for power conversion systems in the U.S. Power Electronics specializes in solar, energy storage, data centers and electrification technologies.

A completion date and operational start date have not yet been announced.

“For the first time in many years, the United States will be able to meet its growing need for sustainable power generation capacity and energy resilience through local manufacturing, supported by the most advanced technology in the world,” David Salvo, CEO of Power Electronics, said in the news release. “Our [40-gigawatt] Houston Campus will help shape the future of energy and AI growth globally."

Once operational, the manufacturing site will feature two buildings of approximately 150,000 square feet and 700,000 square feet. They will house production, logistics, R&D, corporate offices, training and electronic manufacturing departments.

The company says the Houston campus will be its most automated inverter production site by using advanced technologies in production to streamline day-to-day processes. Inverters convert direct current (DC) electricity that is generated by solar panels and batteries to alternating current (AC) electricity used by electrical grids.

Power Electronics' global headquarters is in Valencia, Spain, with U.S. operations in Houston, Tampa, and Gilbert, Arizona. Its North American headquarters is located at its existing North Houston office on East Airtex Drive. Community Impact News reports that the new manufacturing site is located in the Cy-Fair/Jersey Village area.

Power Electronics shared on LinkedIn that the new Houston campus represents its commitment to its American business and will allow it to serve the market with "greater scale, proximity and local expertise." It currently has more than 116 gigawatts installed in the U.S. and is working toward a global goal of 105 gigawatts of annual global production capacity.

At a recent event in Houston, energy transition experts shared opportunities in renewables and sustainability. Photo by Lindsey Ferrell/EnergyCapital

Energy transition opportunities are heading to Texas and beyond, according to these experts

incoming

The energy industry in Houston, Texas, and beyond is gearing up for new opportunities within the energy transition, as a recent Houston event and its lineup of experts shared.

At the inaugural ENERGYEAR USA 2023, panelists outlined how their companies are opting into a more personable approach to building sustainable energy solutions – and sustainable communities.

“Most of our renewable projects are in very rural areas. We come to communities that don’t have enough money to invest in their schools, their kids. There’s not a lot of opportunity,” explains David Carroll, chief renewables officer and senior vice president of the North America region for Engie.

“We come in and invest a lot in the construction phase, but after that, we have workers that live there. We are often one of the largest taxpayers in that area,” Carroll continues. “We can provide them cash profit, provide them the tax base, so that we can help provide a future in many of these rural communities that were struggling before we got there.”

Engie, which has closed several coal plants globally ahead of schedule to work toward meeting their commitment to Net Zero by 2045, isn’t the only organization that emphasizes purpose in its pursuit of energy equity.

Power Electronics, the global leader in renewable energy storage, finds purpose through re-purposing field technicians. For the past five years, the organization has transformed talent with electrical equipment experience from the oil and gas industry into renewables. The company doesn’t plan on slowing down, either.

“We are proud to announce here today [that over] the next two years, we will create more than 500 jobs as the largest ever manufacturer of solar inverter and intermediate scale battery inverters in the U.S.,” shares David Salvo, CEO of Power Electronics. “We start manufacturing EV chargers in Houston later this year and are committed to U.S. manufacturing job creation.”

The company saw a need for setting up a Texas manufacturing facility to support growth and was impressed by the volume of Houston talent possessing a deep understanding of both mechanical and electrical equipment from their tenure in upstream oil and gas.

“It is easier to find people here [like that] than anywhere else,” Salvo tells EnergyCapitalHTX. “That is a fact.”

Explosive growth for the region has barely even begun, with expected investments in Texas alone exceeding $60 billion dollars in large scale renewables.

“Because of these investments that we are making, we are able to create good paying jobs… and meet climate goals of getting to a Net Zero economy by 2050,” Jeff Marootian, U.S Department of Energy senior advisor, tells Katie Mehnert, CEO of Ally Energy and DOE Ambassador, during their fireside chat.

“Partnership between government and private sector, ultimately, is creating these opportunities,” Marootian says. “Our challenge is to help identify, help train, help build up that generation of workforce.”

As a final note on the trifecta of purpose, partnering, and governance, Erika Bierschbach, vice president of energy market operations and resource planning for Austin Energy, challenges the power and utilities industry to embrace statistical models over deterministic ones when forecasting energy supply and demand. The upstream oil and gas sector embraced this practice years ago to improve production optimization processes.

On the subject of green energy employment, a recent report found that Houston is a successful hub when it comes to clean energy jobs. SmartAsset, a personal finance website, recently ranked the Houston metro area as the fifth best place in the U.S. for green jobs, which pay an average of 21 percent more than other jobs. And actually, the study found that 2.23 percent of workers in the Houston area hold down jobs classified as “green.”

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

Feds back Houston-based Grid United's $4B plan to connect U.S. power grids

Powering the Grid

The federal government is backing an electric power line intertie in Wyoming that will double the flow of electricity between the eastern and western grids, the U.S. Department of Energy announced.

Houston-based Grid United’s $4 billion project, backed by a $2.8 billion “conditional” loan from the federal Energy Dominance Financing program, will string high-voltage lines from the Laramie River Station coal-fired power plant outside Wheatland 106 miles west to the Aeolus substation near Medicine Bow.

The bidirectional connection allows for system operators and utilities to flow electricity either direction, “strengthening the grid and giving operators new tools to respond to surges in demand or outages,” Office of Energy Dominance Financing Director Gregory Beard said in a press conference.

“The bridging of these neighboring systems with a transmission line,” Beard added, “provides more reliable energy flows, lowers ratepayer electricity bills and stabilizes the grid, especially during extreme weather conditions.”

Wyoming sits in the western grid, and the edge of the two grids essentially trace Wyoming’s eastern border. Laramie River Station is one of the few power plants with access to both grids, likely making it an ideal location to beef up a connection between the two systems, Wyoming Energy Authority Director of Energy Market Development John Jenks told WyoFile.

“It adds flexibility to energy being dispatched onto the grid,” Jenks said. “We can send electricity east if we have excess electricity, or we can take it from the east. For Wyoming electricity producers, it’s expanding the markets to dispatch and sell their electricity.”

Though the project does not rely on building additional electrical generation capacity, it will certainly enable new power projects, Beard said. “There are certainly growing electricity demands nationwide and on both sides of this interconnect. So this (helps) solve a current problem.”

The three-year construction of the intertie is expected to begin in 2030. Once completed, it is estimated to save ratepayers in Wyoming and 17 other states a combined $39 billion in avoided costs over the next 30 years, according to the DOE. Beard underscored the estimated savings, crediting President Donald Trump for his “energy dominance” initiatives, including his Strengthening the Reliability and Security of the U.S. Electric Grid executive order.

However, Jenks cautioned that the intertie won’t necessarily lower rates for Wyoming customers. It could avoid occasional price spikes, which are passed on to customers, by providing flexibility to ship available power to where it’s needed during times of imbalance.

“It can dispatch generation resources more efficiently, which should — in theory — lower electricity bills,” he said. “It might be a stretch to say it will (lower monthly bills), but that’s the theory behind it.”

The Platte County to Carbon County route consists of about 90% state and federally owned land, according to Beard, and the project may receive fast-track permitting.

“This is not going to have issues around land acquisition or condemning properties to put the transmission line up,” he said. “There will not be protests in the street over condemning land to get this line up.”

Grid United says it’s still working with tribal nations and landowners to finalize the route.

“The route will remain proposed until it receives approval from county, state and federal regulatory bodies,” according to the company’s Wyoming Intertie website. “Construction will commence after Wyoming Intertie secures land rights and regulatory approvals.”

Houston’s Giga Energy lands $1B lease at AI data center

A Houston manufacturer of modular data centers has secured a $1 billion customer for its latest project.

Giga Energy signed a 10-year lease with an unidentified U.S. company that provides AI cloud computing services. The lease is for Project Clay, a 60-megawatt AI data center that Giga Energy is building in Hunt County, about 55 miles northeast of Dallas. Giga Energy will develop, own and operate the facility.

Construction at the 30-acre site began in July. Operations are set to start next spring.

Much of the facility isn’t actually being built in Hunt County. Giga Energy is prefabricating significant portions, then shipping components to Hunt County for final assembly. The company operates factories in Houston and Long Beach, California.

The company says this approach shortens construction time and reduces disruption to local roads, housing and traffic. As such, communities can start seeing economic benefits more quickly, Giga Energy says.

Project Clay is the first site to use GigaBase, Giga Energy’s new data-center model. GigaBase addresses some of the main objections to data centers: long build times, heavy consumption of water and extra electrical loads for local utilities.

Power and water

At full capacity, Project Clay would provide enough electricity to power about 15,000 Texas households at peak demand on the state’s main power grid. The Electric Reliability Council of Texas (ERCOT) manages that grid, which supplies about 90 percent of Texas’ electricity.

To keep power demand from competing with local users, Giga Energy plans to build new electrical infrastructure that uses idle capacity on existing lines, not the distribution capacity that serves homes and businesses in the area.

Giga Energy will cool its servers with a closed-loop system that doesn’t depend on the local water supply, avoiding the water-intensive evaporative cooling many data centers use. The only local water at the site will be used for restrooms and sinks.

The company says these steps line up with standards Texas Governor-elect Gina Hinojosa has proposed for data centers, such as covering their own power costs and cooling their facilities with water-efficient technology.

“This is exactly the kind of AI infrastructure Texas needs,” Brent Whitehead, Giga Energy’s co-founder and president, said in a news release. “Communities shouldn’t have to choose between economic growth and protecting local resources.”

Jobs and tax revenue

Giga Energy expects Project Clay to employ about 300 people during construction. Once the data center is running, it will have 24 full-time employees earning anticipated annual salaries of $116,000 to $180,000. The company also expects the project to generate millions of dollars of annual tax revenue in Hunt County.

Whitehead said that with Project Clay, Hunt County is getting “an economic engine that will support schools, public services, and future growth for generations.”

UH researcher examines the future of carbon capture projects in Texas

carbon paper

University of Houston Law Center research scholar Qaraman Hasan is tackling how Texas can advance carbon capture projects while simultaneously addressing public concerns and environmental issues in a new article in the Harvard Environmental Law Review.

The CCS process includes capturing carbon dioxide emissions and storing them underground with the goal of preventing them from influencing the environment and adding to pollution. In November 2025, Texas received federal approval to take over permitting authority, or primacy, of Class VI wells. Class VI wells insert CO2 into deep rock formations.

In his article “From Federal Permitting to Primacy: Balancing Environmental Protection and Climate Policy Objectives,” Hasan looks at how state and federal policy around CCS projects in Texas can be balanced with climate policy objectives, environmental protections, and community input. Currently, Hasan teaches environmental and energy law courses at the UH Law Center.

“I hope the article expands the conversation,” Hasan said in a news release. “We have the technology and the legal tools. What remains is better regulation and more constructive dialogue at the state and federal levels, so we can reduce emissions in the states and cities most burdened by pollution and store carbon securely.”

Ultimately, Hasan argues that the goal should be to streamline permitting while supporting industry development and ensuring communities feel safe and have their voices heard. The article highlights the importance of carbon capture and removal for greener climate initiatives, utilizing a Texas case study to conduct his analysis on primacy. It also considers the future sustainability and seismic ramifications of underground storage space, federal permitting processes, and how the public, agencies and AI tools can be used to approach applications.

The Intergovernmental Panel on Climate Change (IPCC) recommended CCS as an option for climate change mitigation over 20 years ago. According to the article, the Department of Energy says that reaching net-zero carbon emissions in the United States would require capturing and sequestering 400 million to 1,800 million tonnes each year until 2050.

The Biden administration previously established a goal of achieving net-zero emissions through several key strategies, including expanding carbon removal and decarbonizing electricity. Hasan notes that environmental regulations are often cited as barriers to low-carbon economy projects, but argues that effective legislation can help advance these projects without overlooking environmental impacts. He also acknowledges that permitting requirements can create initial delays.

“CCS is a significant tool for reducing emissions and protecting the environment, and it should not be dismissed out of hand,” Hasan added in the news release. “It is also one of the few climate areas with bipartisan support, which matters. With that support, it makes sense to give states the authority to regulate it when they meet federal standards, as long as safeguards are in place.”

Read Hasan’s full article here.