Fervo Energy has closed financing to support the remaining construction costs for the first phase of Cape Station. Photo via fervoenergy.com

Houston geothermal unicorn Fervo Energy has closed $421 million in non-recourse debt financing for the first phase of its flagship Cape Station project in Beaver County, Utah.

Fervo believes Cape Station can meet the needs of surging power demand from data centers, domestic manufacturing and an energy market aiming to use clean and reliable power. According to the company, Cape Station will begin delivering its first power to the grid this year and is expected to reach approximately 100 megwatts of operating capacity by early 2027. Fervo added that it plans to scale to 500 megawatts.

The $421 million financing package includes a $309 million construction-to-term loan, a $61 million tax credit bridge loan, and a $51 million letter of credit facility. The facilities will fund the remaining construction costs for the first phase of Cape Station, and will also support the project’s counterparty credit support requirements.

Coordinating lead arrangers include Barclays, BBVA, HSBC, MUFG, RBC and Société Générale, with additional participation from Bank of America, J.P. Morgan and Sumitomo Mitsui Trust Bank, Limited, New York Branch.

“As demand for firm, clean, affordable power accelerates, EGS (Enhanced Geothermal Systems) is set to become a core energy asset class for infrastructure lenders,” Sean Pollock, managing director, project Finance at RBC Capital Markets, said in a news release. “Fervo is pioneering this step change with Cape Station, a vital contribution to American energy security that RBC is proud to support.”

The oversubscribed financing marks Cape Station’s shift from early-stage and bridge funding to a long-term, non-recourse capital structure, according to the news release.

“Non-recourse financing has historically been considered out of reach for first-of-a-kind projects,” David Ulrey, CFO of Fervo Energy, said in a news release. “Cape Station disrupts that narrative. With proven oil and gas technology paired with AI-enabled drilling and exploration, robust commercial offtake, operational consistency, and an unrelenting focus on health and safety, we have shown that EGS is a highly bankable asset class.”

Fervo continues to be one of the top-funded startups in the Houston area. The company has raised about $1.5 billion prior to the latest $421 million. It also closed a $462 million Series E in December.

According to Axios Pro, Fervo filed for an IPO that would value the company between $2 billion and $3 billion in January.

Quaise Energy is developing Project Obsidian, a superhot geothermal plant in central Oregon. Rendering via quaise.com.

Houston cleantech startup seeks $200M for superhot geothermal plant

seeing green

Houston-based Quaise Energy is looking to raise $200 million to support the development of a 50-megawatt superhot geothermal plant in Oregon.

The company is seeking $100 million in Series B funding, plus an additional $100 million from grants, debt and project-level finance, a representative from the company tells Energy Capital. Axios first reported the news late last month.

Quaise specializes in terawatt-scale geothermal power. It is known for its millimeter-wave drilling technology, which was developed at MIT.

The company's Project Obsidian development in central Oregon will combine conventional drilling with its millimeter-wave technology. Quaise says the project, targeted to come online in 2030, could be the first commercial plant to operate in superhot rock, a more efficient and abundant resource, but one that requires more advanced and durable drilling technology.

Quaise says Obsidian would initially generate 50 megawatts of "always-on" power and would be designed to add 200 megawatts as additional wells are developed. A power-purchase deal has already been signed for the initial 50 megawatts with an undisclosed customer.

A representative from the company says Quaise would also use the funding to continue advancing its millimeter-wave technology and prepare it for commercialization.

Last year, the company drilled to a depth of about 330 feet using its millimeter-wave technology at its field site in Central Texas.

“Our progress this year has exceeded all expectations,” Carlos Araque, CEO and president of Quaise Energy, said at the time. “We’re drilling faster and deeper at this point than anyone believed possible, proving that millimeter-wave technology is the only tool capable of reaching the superhot rock needed for next-generation geothermal power. We are opening up a path to a new energy frontier.”

Canary Media reports that Quaise plans to drill to nearly 3,300 feet later this year and to deploy its millimeter-wave technology at its power plant in 2027.

Quaise raised $21 million in a Series A1 financing round in 2024 and a $52 million Series A in 2022. Major investors include Prelude Ventures, Safar Partners, Mitsubishi Corporation, Nabors Industries, TechEnergy and others.

Quaise was one of eight Houston-area companies to appear on Time magazine and Statista’s list of America’s Top GreenTech Companies of 2025.

Ad Placement 300x100
Ad Placement 300x600

CultureMap Emails are Awesome

ERock scores Anthropic deal, sees order backlog soar to $1.7B

power deal

Two months after its $400 million IPO, Houston-based ERock (NYSE: EROC) has landed a power-generator deal with AI powerhouse Anthropic, owner of the Claude platform.

In its Q2 earnings report, ERock says it will provide equipment to Anthropic with a 470-megawatt capacity. ERock specializes in utility-grade, onsite microgrid power systems for data centers and other customers. The company previously did business as Enchanted Rock.

The Anthropic deal adds to ERock’s backlog of about $1.7 billion in orders—a figure representing a 1,000 percent year-over-year jump in backorders thanks in large part to the AI boom. ERock expects most of the backlog to convert to revenue by the end of 2027, said Ian Blakely, the company’s chief financial officer.

Bank of America analyst Ross Fowler says the Anthropic contract boosts confidence in ERock’s ability to secure other major deals, according to Traders Union. The Anthropic deal is ERock’s third major data center contract, with separate Anthropic deals for operations and maintenance services expected to follow, Fowler said.

CEO John Carrington says Anthropic’s order “reinforces the momentum” ERock is witnessing across its customer base.

“We are seeing a lot of interest in Texas. It seems to be the easiest place to get a site set up,” company President Corey Amthor said

In its Q2 earnings release—its first as a public company—ERock also reported:

  • Launching generator-assembly operations at its Hyperion equipment factory in Northwest Houston. The plant will expand ERock’s assembly capabilities to 1.2 gigawatts of capacity by the end of 2026.
  • Starting construction of a $473 million, 366-megawatt El Paso Electric natural-gas-powered plant to supply power for Meta Platforms’ $14 billion, 1,000-acre AI data center campus in El Paso. Meta is the parent company of the Facebook and Instagram social media companies.

“Meta gains access to an operational data center years earlier than may otherwise be possible, while El Paso Electric gains a flexible, low-cost, low-emissions grid asset that can support long-term system reliability,” Carrington said.

Nominate energy trailblazers for Houston Innovation Awards by Aug. 27

Awards Season

Calling all energy innovators: The 2026 Houston Innovation Awards, presented by InnovationMap, return this fall to celebrate the best and brightest in the Houston innovation ecosystem, and that includes those leading the energy transition.

We're asking you to nominate Houston's top innovators and startups for this year's awards.

Nominations are open now through August 27 and can be made on behalf of yourself, your organization, and other influential leaders in the local innovation scene.

The annual awards program recognizes the most innovative individuals and companies in Houston across 10 prestigious categories, including one category specifically for the energy transition.

This year's awards will honor the following categories:

  • Minority-founded Business, honoring an innovative startup founded or co-founded by BIPOC or LGBTQ+ representation.
  • Female-founded Business, honoring an innovative startup founded or co-founded by a woman.
  • Energy Transition Business, honoring an innovative startup providing a solution within renewables, climatetech, clean energy, alternative materials, circular economy, and beyond.
  • Health Tech Business, honoring an innovative startup within the health and medical technology sectors.
  • Deep Tech Business, honoring an innovative startup providing technology solutions based on substantial scientific or engineering challenges, including those in the AI, robotics, and space sectors.
  • Startup of the Year (People's Choice), honoring a startup celebrating a recent milestone or success. The winner will be selected by the community via an interactive voting experience.
  • Scaleup of the Year, honoring an innovative later-stage startup that's recently reached a significant milestone in company growth.
  • Incubator/Accelerator of the Year, honoring a local incubator or accelerator that is championing and fueling the growth of Houston startups.
  • Mentor of the Year, honoring an individual who dedicates their time and expertise to guide and support budding entrepreneurs.
  • Trailblazer, honoring an innovator who's made a lasting impact on the Houston innovation community.

You have three weeks to submit nominees, so don't delay — nominate today at this link or fill out the form below. Qualified nominees will receive a formal application to complete, which will be reviewed by our esteemed panel of judges to determine the finalists and winners.

More announcements about the 2026 Houston Innovation Awards are coming soon. Interested in sponsoring the 2026 Houston Innovation Awards? Please contact sales@innovationmap.com.

Telsa eyes Houston area for $10 billion solar manufacturing plant

under review

Electric vehicle and clean energy company Tesla is considering building a new $10.1 billion solar cell manufacturing facility in Fort Bend County, according to documents filed with the Texas Comptroller’s Office.

If approved, the plant, called Project Sun City, would be located on a 3,050-acre site off FM 762 and FM 1994 in Richmond, Texas. Tesla aims to finish construction in 2028, with the plant being operational by early 2029.

The plant will manufacture photovoltaic (PV) solar cells and modules that can convert sunlight into electricity. PV Magazine reports that the facility is "the largest single manufacturing investment Tesla has proposed on paper."

Advisory and consulting firm Kroll submitted the documents to the Texas Comptroller of Public Accounts and noted if an agreement regarding tax incentives isn't reached, the project will exit Texas.

Tesla has requested credits under the Jobs, Energy, Technology, and Innovation (JETI) Act. The incentive program aims to attract large, capital-intensive economic development projects by lowering the property taxes an entity must pay over 10 years if it meets requirements related to job creation and investment. For example, pharmaceutical giant Bristol Myers Squibb Co. recently announced that its forthcoming $2.3 billion Houston-area manufacturing site is a qualified project under the JETI program.

Kroll predicts that the facility would create 9,712 new full-time jobs, over 1,100 construction jobs and billions of dollars in future property tax revenue, the documents show. Additionally, it says the project will spur $1.1 billion in local business expenditures and that Texas would increase its GDP by approximately $107 billion as a result of the project activities.

Tesla opened its $200 million Megafactory in Brookshire, Texas, last year. The company is continuing its goal to deploy 100 gigawatts of solar manufacturing in the U.S before the end of 2028. According to the U.S. Energy Information Administration, 100 gigawatts is equal to about 8 percent of the country's power grid capacity.